AMARA AANYA

TN/29/Building/0456/2024 · TNRERA · https://gethorizon.in/projects/amara-aanya-yk8h5x2j

01

Complete project overview

TNRERA · Registration filing
Description
Registration of High Rise Group Development Residential Building consist of Block No.1: with extended Tripple Basement Floor (Meant for parking) + Stilt Floor part (Meant for parking)/G.Floor part (for Gym) + 1st Floor to 17th Floor with 34 Dwelling units & Swimming Pool at Terrace floor and Block No.2: Stilt Floor (Meant for parking & Association room) + 1st Floor to 5th Floor with 5 Dwelling units. Totally 39 dwelling units, availing Premium FSI with TOD Benefit at Door No.187/121, 191/122, St.Mary’s Road, Alwarpet, Chennai – 600 018, Comprised in R.S.No.3925/5, 3925/22, 3926/1, 3926/4, Block No.86, Mylapore Village, Mylapore Taluk, Chennai District.
Registration no.
TN/29/Building/0456/2024

Timeline

RERA registeredAug 2024
Proposed completionJan 2029
TodaySep 2026
02

Builder’s track record

TNRERA · Builder registration

A.R.FOUNDATIONS PRIVATE LIMITED

A.R.FOUNDATIONS PRIVATE LIMITEDPromoter
3Projects
1Cities
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
3 projectson the public record across 3 projects

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from A.R.FOUNDATIONS PRIVATE LIMITED— the full portfolio →

03

Location

TNRERA · Registration filing
What’s nearby
Schools1 school within 1km · 4 educational institutions within 1km · College or university 1.9km away
HealthcareHospital 290m away · 8 clinics within 1km · Pharmacy within 500m
LifestyleNo parks within 2km · 34+ restaurants and cafes within 1km
ShoppingSupermarket 304m away · Mall 1.6km away · Convenience store within 500m
Getting around
Primary road 979 m · Anna Salai (Mount Road)Railway line 684 m · MRTSRailway station 802m away (Greenways Road)9 bus stops within 500m
Water & environment
Canal 713 m · Buckingham CanalRiver 1.1 km · Adyar River
distances only — not a flood assessment
04

Government Guidance Rate

Tamil Nadu registration department

In Tamil Nadu it’s called the guideline value.

No government guidance rate is shown for this project.

Tamil Nadu publishes street-level guideline values; its full schedule isn't in Horizon's record yet.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

TNRERA · Approved building plan

CMDA (Chennai Metropolitan Development Authority)

CMDA (Chennai Metropolitan Development Authority)
approved 20 Aug 2024 · 2 yrs ago
Planning Permission no. OL-PP/HRB/0020/2024
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

Verify it yourself — look up plan OL-PP/HRB/0020/2024 on the approving authority’s portal to confirm the approval.

The approving body, at scale

CMDA (Chennai Metropolitan Development Authority)

Metropolitan development authority

Has approved 1,914 RERA projectsabout 1 in 2 in Tamil Nadu, more than any other body in the state.

Builders
1,310
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by TNRERA

07

Other projects nearby

The register · within 25 km

466 residential and mixed-use projects still under way within 25 km. Step out ring by ring:

Of the 198 projects the radar draws within 6 km — every kind, every stage — 158 are residential and mixed-use projects still under way. This list keeps only those, and looks further out.

9 projects within 1 km — showing the nearest 6.

170 m away

KENZ KREST

INDIA BUILDERS CHENNAI LIMITED (Developer)

Sep 2025registered
Dec 2030target completion
AuthorityTNRERA
190 m away

RAGHU

Ms INDIA BUILDERS CHENNAI LIMITED 1.PREMILA HARIMOHAN 2.VIDYA SHANKAR 3.BHANUMATHI KANNAN 4.(i) C.V.MURALI (ii) RAGHU VENKAT NARAYAN 5.C.S.VEERARAGHAVAN 6.B.KANAKARAJU

Jan 2026registered
Dec 2030target completion
AuthorityTNRERA
350 m away

SWATHI'S VARUN

SWATHI BUILDERS

Feb 2025registered
Dec 2029target completion
AuthorityTNRERA
430 m away

UPPER HOUSE

CEEBROS HOTELS PRIVATE LIMITED Rep by Managing Director Thiru.C.SUBBA REDDY & GPA Holders Tvl.1.R.V.SUNDAR & 2.K.SATHISH

Oct 2024registered
Dec 2027target completion
AuthorityTNRERA
510 m away

VISHRANTHI CITADEL

Vishranthi Homes Private Limited

Sep 2026registered
Dec 2031target completion
AuthorityTNRERA
520 m away

TN/29/Building/0322/2024

TAGROS CHEMICALS INDIA PVT LTD

Apr 2024registered
Apr 2028target completion
AuthorityTNRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — TNRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — TNRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — TNRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.