10 filed — Community Center, Elecricity Supply, External Road, Fire Fighting Facility, Gym/fitness center, Internal Road …
Description
B1+B2+G+12 Multi Storied Residential Apartment Building
Timeline
Construction startAug 2025
Proposed completionJan 2028
TodaySep 2026
Find your flat
Every flat the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.
UnitCarpet sq m
1011ST FLOOR153.62
1021ST FLOOR106.32
1031ST FLOOR153.62
1041ST FLOOR115.57
1051ST FLOOR115.57
2012ND FLOOR153.62
2022ND FLOOR106.32
2032ND FLOOR153.62
2042ND FLOOR115.57
2052ND FLOOR115.57
3013RD FLOOR153.62
3023RD FLOOR106.32
3033RD FLOOR153.62
3043RD FLOOR115.57
3053RD FLOOR115.57
4014TH FLOOR153.62
4024TH FLOOR106.32
4034TH FLOOR153.62
4044TH FLOOR115.57
4054TH FLOOR115.57
5015TH FLOOR153.62
5025TH FLOOR106.32
5035TH FLOOR153.62
5045TH FLOOR115.57
5055TH FLOOR115.57
6016TH FLOOR153.62
6026TH FLOOR106.32
6036TH FLOOR153.62
6046TH FLOOR115.57
6056TH FLOOR115.57
7017TH FLOOR153.62
7027TH FLOOR106.32
7037TH FLOOR153.62
7047TH FLOOR115.57
7057TH FLOOR115.57
8018TH FLOOR153.62
8028TH FLOOR106.32
8038TH FLOOR153.62
8048TH FLOOR115.57
8058TH FLOOR115.57
9019TH FLOOR153.62
9029TH FLOOR106.32
9039TH FLOOR153.62
9049TH FLOOR115.57
9059TH FLOOR115.57
100110 FLOOR153.62
100210 FLOOR106.32
100310 FLOOR153.62
100410 FLOOR115.57
100510 FLOOR115.57
110111TH FLOOR153.62
110211TH FLOOR106.32
110311TH FLOOR153.62
110411TH FLOOR115.57
110511TH FLOOR115.57
120112TH FLOOR153.26
120212TH FLOOR106.32
120312TH FLOOR153.62
120412TH FLOOR115.57
120512TH FLOOR115.57
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. Carpet area is the legally meaningful number — not the super built-up figure a brochure quotes.
All 60 units as filed, two to a row · areas in sq m
The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Expressway 3.9 kmPrimary road 946 m · Ring RoadRailway line 3.5 kmRailway station 3.5km away (Cuttack Junction)Limited bus connectivity nearby
Water & environment
Water body 47 mRiver 2.5 km · Mahanadi
distances only — not a flood assessment
Land, title & encumbrance
Land parcels2 parcels · 2,343 sq m total
Land tenure1 of 2 parcels held under a Power of Attorney / development agreement — not a registered sale deed to the promoter
VillageUnit No-13,Chandin Chowk
As declared by the builder at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Location — done
04
Government Guidance Rate
Odisha registration department
In Odisha it’s called the benchmark value.
No government guidance rate is shown for this project.
Odisha's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
05
Planning authority
ORERA · Approved building plan
Cuttack Municipal Corporation
Municipal / Corporation
Building Permit
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
The approving body, at scale
Cuttack Municipal Corporation
Municipal / Urban Local Body
Has approved 36 RERA projects — 3% of Odisha.
an apartments market — 94% apartments · 6% plotted layouts. Apartments like yours are this body's core business.
Builders
31
On record
13,427 flats · 69 plots
Reach
15 pincodes
Since
2021
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
Not published. ORERA doesn’t publish a complaints register in the record Horizon reads.
So there is nothing to count here — which is not the same as nothing having been filed.
What the builder declared
Declared to ORERA
Litigation
None declared in this filing
Only what the builder declared, or what ORERA records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with ORERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
07
Other projects nearby
The register · within 25 km
308 residential projects still under way within 25 km. Step out ring by ring:
Of the 61 projects the radar draws within 6 km — every kind, every stage — 28 are residential projects still under way. This list keeps only those, and looks further out.
2 projects within 1 km — showing the nearest 2.
CuttackMixed Development
SRC SIGNATURE
SHREE RAM CONSTRUCTIONS
PossessionMay 2027Scale220 flatsRegistrationvalid to Jul 2025
No government guidance rate could be matched to this project from Odisha's published schedules.
05Planning authority
ORERA: the approved building plan, as filed.
The approving body's other projects: counted by Horizon across the register.
06Complaints & litigation
ORERA's public record lists no complaints or litigation for this project.
07Other projects nearby
The RERA-registered projects Horizon holds within 25 km of these coordinates.
Compiled by Horizon from public records. Each fact is reproduced as its source publishes it, and Horizon does not verify filings on the ground. The live record: gethorizon.in/projects/jain-exotica-chandin-chowk-cuttack-5ccwae3o.
Horizon does not rate, review, score or signal, and it gives no verdict, opinion or forecast. Its only aim is to seek the truth through data: what the public record says, where each fact comes from, and where the record is silent. Nothing in this document is legal, financial or investment advice; what to make of it is yours to decide.