HORIZONMarkets
01

Complete project overview

RAJ-RERA · Registration filing
Land area
3,510 sq m
Description
1. apartment type detail & its related details have been modified on 234.07.2021 2. Revised Land cost & Development cost should be read as Land cost as per rule 5(1)= 15,90,01,183/- Development cost as per rule 5(2)= 16,45,59,573/- TOTAL COST OF THE PROJECT= 32,21,70,635/-instead of old Land cost & Development cost All above details have been changed on application of applicant and Remark add on 24.07.2021

Timeline

Construction startJun 2016
RERA registeredAug 2017
Proposed completionDec 2020
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

Shri Khatu Shyam Builders

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2017–2020Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
1, Siddharth Nagar H Block Manoharpura near Jawahar Circle, jaipur, Jaipur, Jaipur, 302017
Village
jaipur
Taluka
Jaipur
District
Jaipur
Pincode
302017
What’s nearby
SchoolsNearest school 1.1km away
HealthcareHospital 235m away · Clinic within 2km
LifestyleNo parks within 2km · Gym or sports centre 1.2km away · 5 restaurants and cafes within 1km
ShoppingSupermarket 1.0km away · Mall 726m away · Bank 263m away
Getting around
Expressway 3.6 kmPrimary road 675 mRailway line 890 mRailway station 2.4km away (Durgapura)3 bus stops within 500m
Price analysisdeclared build cost — not a sale price

₹32.36 Cr declared. What that works out to:

49%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Jaipur Development Authority

Development Authority
Building Permitapproved 29 Aug 2017 · 8 yrs ago

The promised possession date (31 Dec 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Jaipur Development Authority

Development authority

Has approved 644 RERA projectsabout 1 in 3 in Rajasthan, more than any other body in the state.

a mixed market52% apartments · 48% plotted layouts.

Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017

More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.