Complete project overview

RAJ-RERA · Registration filing
Land area
8,099 sq m
Completion deadline extended
4 extensions on record — latest to 1 Jun 2021declared reason: force majeure
Description
1. As per applicant request application, and further to the approval of Hon'able chairman on 24.12.2019,estimated finish date,has been extended from 31.05.2018 to 31.05.2019. The estimated finish date has been changed on 03/01/2020.Therefore the revised estimated finish date should be read as 31.05.2019. 2. The project has been extended beyond one-year w.r.t. Authority order dated 22-05-2020 on 03-07-2020. This bears the approval of Honorable Chairman, before extension beyond one year the estimated finish date of the project was 31-05-2019. 3. Revised maps with subsequent changes updated on 03-07-2020. Updated Building Plans uploaded in the "Building Sanction Plan" column.

Timeline

Construction startApr 2015
RERA registeredAug 2017
Proposed completionMay 2020
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

FS HOUSING PRIVATE LIMITED

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2017–2020Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
A-4, AIRPORT ENCLAVE SCHEME, TONK ROAD, DURGAPURA, Jaipur, Jaipur, 302018
Taluka
Jaipur
District
Jaipur
Pincode
302018
What’s nearby
SchoolsNearest school 1.8km away · College or university 1.9km away
HealthcareHospital 105m away · 7 clinics within 1km · Doctor's clinic within 1km
LifestyleNo parks within 2km
ShoppingSupermarket 647m away · Mall 787m away · ATM within 500m
Getting around
Expressway 2.6 km · FlyoverPrimary road 225 m · Durgapura FlyoverRailway line 876 m · Jaipur to Sawai Madhopur LineRailway station 1.4km away (Durgapura)Bus stop within 1km
Water & environment
Water body 1.6 km · Dravyavati River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹264.71 Cr declared. What that works out to:

45%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 17 Aug 2017 · 8 yrs ago

The promised possession date (31 May 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.