Complete project overview

RAJ-RERA · Registration filing
Land area
8,236 sq m
Completion deadline extended
1 extension on record — latest to 31 Mar 2021declared reason: force majeure
Description
1. Approved building plans dated 07.09.2017 by JDA for 3 Basements + Ground + Service +2 Floors have updated on 30.09.2020. This bears the approval of Honorable Chairman Sir.

Timeline

Construction startFeb 2016
RERA registeredAug 2017
Proposed completionMar 2020
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

NIMRANA DEVELOPERS

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2017–2020Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
1, AIRPORT PLAZA, TONK ROAD, JAIPUR, Jaipur, Jaipur, 302016
Village
JAIPUR
Taluka
Jaipur
District
Jaipur
Pincode
302016
What’s nearby
SchoolsNearest school 2.0km away · College or university 1.9km away
HealthcareHospital 79m away · 3 clinics within 1km
LifestyleNo parks within 2km
ShoppingSupermarket 669m away · Mall 745m away · ATM within 500m
Getting around
Expressway 2.5 km · FlyoverPrimary road 105 m · Durgapura FlyoverRailway line 947 m · Jaipur to Sawai Madhopur LineRailway station 1.5km away (Durgapura)Bus stop within 1km
Water & environment
Water body 1.5 km · Dravyavati River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹226.00 Cr declared. What that works out to:

47%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 8 Aug 2017 · 8 yrs ago

The promised possession date (31 Mar 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.