PANDURANGPARK

P99000020314 · MahaRERA · https://gethorizon.in/projects/pandurangpark-saravali-palghar-cbot6s2v

01

Complete project overview

MahaRERA · Registration filing
Project name
PANDURANGPARK
Units
96 units
Floors
6
Buildings
23
Parking
36 spaces
Land area
8,770 sq m
Sanctioned built-up
9,190 sq m
Recreational open space
926 sq m

Timeline

RERA registeredApr 2019
Proposed completionJun 2026
TodaySep 2026
Construction progress
Basement (if any)0%
Podiums0%
Water Supply0%
Storm Water Drains0%
Solid Waste Manage…0%
Water conservation…0%
Aggregate area of …0%
Open Parking0%
Landscaping & Tree…10%
Street Lighting20%
Treatment And Disp…20%
Internal Roads & F…50%
Sewerage (Chamber,…80%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
External finishes100%
OC-readiness100%
Stairs & lifts1000%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

CHAITANYA BUILDERS & DEVELOPERS

PartnershipPromoter type
Palghar, MAHARASHTRABased in
2Projects
2Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
145 homeson the public record across 2 projects
11,909 sq mbuilt-up filed
9,470 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
City and Industrial Development Corporation (CIDCO)Development Authority1 of 2 projects
CollectorCollector officethis project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from CHAITANYA BUILDERS & DEVELOPERS— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Saravali
Taluka
Palghar
District
Palghar
Pincode
401501
Survey no.
139/1
North boundary
baburav gharat house
East boundary
sandip gharat house
South boundary
baban gharat house
West boundary
s no 139
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 242m away · 7 clinics within 1km
LifestyleNo parks within 2km · Playground within 500m
ShoppingNo supermarket within 2km · Bank 618m away · ATM within 500m
Getting around
Primary road 273 m · Boisar-Palghar RoadRailway line 133 mRailway station 323m away (Boisar)Limited bus connectivity nearby
Water & environment
Canal 2.5 kmWater body 3.6 km
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹20,903per sq yd
₹25,000per sq m
Which rate
residential building or flat
Matched to
The rate published for the village of “Saravali”.
In force
2026-2027 schedule

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Collector

Collector office
Building Permit
Survey no. 139/1

The promised possession date (30 Jun 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Collector

Planning authority

Has approved 47 RERA projects0.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
38
On record
106 flats · 0 plots
Reach
4 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

300 residential projects still under way within 25 km. Step out ring by ring:

Of the 254 projects the radar draws within 6 km — every kind, every stage — 79 are residential projects still under way. This list keeps only those, and looks further out.

8 projects within 1 km — showing the nearest 6.

KambalgaonResidential / Group Housing

SHREE PURAM TOWNSHIP BUILDING NO 2B

SMRITI HOUSING PRIVATE LIMITED

Feb 2021registered
Jun 2028target completion
Government Guidance Rate₹32,275/sq ydScale26 flatsAuthorityMahaRERA
BoisarOthers

PALASH

INFRA CRAFTS

Sep 2019registered
Dec 2027target completion
Scale61 flatsAuthorityMahaRERA
KurgaonResidential / Group Housing

Bhakti Avenue

Bhakti Green Realty LLP

Jul 2025registered
Mar 2027target completion
Scale30 flatsAuthorityMahaRERA
BoisarOthers

Yash Padma Phase II

SAI SHRADDHA ENTERPRISES

Mar 2024registered
Dec 2030target completion
Scale66 flatsAuthorityMahaRERA
KurgaonResidential / Group Housing

EMERALD WOODS 2

SHREHIT DEVELOPERS

Jun 2023registered
Dec 2029target completion
Scale105 flatsAuthorityMahaRERA
BoisarResidential / Group Housing

OSTWAL PARAMOUNT

SHREE OSTWAL BUILDERS LTD

Nov 2024registered
Dec 2029target completion
Scale81 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.