Complete project overview

RAJ-RERA · Registration filing
Units
80 units
Mix
40 × 3 BHK · 40 × 2 BHK
Carpet area
79–115 sq mper-type range, as filed
Land area
5,613 sq m
Description
The Project is being registered as Ongoing project. This project has 2 blocks, Block -B, which has been completed, and Block -A, which is almost 80% completed and for registration of which this application is being made. Block B completion certificate received and submitted to RERA. Hence this application is being made for only block A only. Initially we have wrongly mentioned the phase area is 2297.00 Sq. Mtrs, however the correct phase area is 2629.62 Sq. Mtrs, therefore, remaining fees has been paid accordingly.As per remark the correct phase area has been rectified in Land Details of Registering Project.

Timeline

Construction startJan 2013
RERA registeredFeb 2020
Proposed completionDec 2022
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

80 units across 8 batches
BuildingTypeArea sq mCount
SHREE ENCLAVE3 BHK10910
SHREE ENCLAVE2 BHK8210
SHREE ENCLAVE2 BHK8910
SHREE ENCLAVE3 BHK11510
SHREE ENCLAVE3 BHK11110
SHREE ENCLAVE2 BHK9210
SHREE ENCLAVE2 BHK7910
SHREE ENCLAVE3 BHK11210

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

PARTH INFRATECH PRIVATE LIMITED

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2020–2022Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
87/1, Gram Harnathpura, Niwaru Road, Jaipur Th. Jaipur- , Jaipur, Jaipur, 302012
Taluka
Jaipur
District
Jaipur
Pincode
302012
What’s nearby
SchoolsNearest school 1.1km away
HealthcareHospital 599m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingSupermarket 1.7km away
Getting around
Expressway 476 m · FlyoverPrimary road 1.7 kmRailway line 3.0 kmRailway station 3.9km away (Dahar-Ka-Balaji)Bus stop within 500m
Water & environment
Water body 3.9 km · ghodela bulding material
distances only — not a flood assessment
Land, title & encumbrance
Litigation1 case on record — Arbitration Suit (2016)
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹65.00 Lakh declared to build 80 flats. What that works out to:

₹81,250declared cost per flatall-in — land + construction
₹33/sq ftof built-up area₹353/sq m

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Jaipur Development Authority

Development Authority
Building Permitapproved 10 Feb 2020 · 6 yrs ago

The promised possession date (31 Dec 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Jaipur Development Authority

Development authority

Has approved 644 RERA projectsabout 1 in 3 in Rajasthan, more than any other body in the state.

a mixed market52% apartments · 48% plotted layouts.

Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017

More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.