Complete project overview

MahaRERA · Registration filing
Units
298 units
Mix
166 × 1 BHK · 46 × 3 BHK · 33 × 2.5 BHK · 33 × 2 BHK · 12 × Shop · 8 × 4 BHK
Carpet area
13–597 sq mper-unit range, as filed
Floors
44
Buildings
2
Parking
300 spaces
Land area
5,211 sq m
Sanctioned built-up
19,952 sq m

Timeline

RERA registeredMar 2025
Proposed completionDec 2031
TodayJul 2026
Construction progress
Excavation0%
Basement (if any)0%
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

298 units across 19 batches
TypeArea sq mCount
Shop311
4 BHK1653
4 BHK1625
3 BHK11110
Shop5971
3 BHK8936
2.5 BHK6833
2 BHK5333
Shop481
Shop851
Shop3911
Shop2041
Shop1091
Shop131
Shop141
Shop261
Shop241
1 BHK28166
Shop241

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

Starom Sejal Realbuild LLP

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Malad
Taluka
Borivali
District
Mumbai Suburban
Pincode
400064
Survey no.
C.T.S. No- 524, 524/1 to 16
North boundary
CTS No-516A
East boundary
CTS No-523B
South boundary
Marve Road
West boundary
CTS No-523
What’s nearby
SchoolsNearest school 1.8km away
HealthcareHospital 1.6km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingSupermarket 933m away
Getting around
Primary road 3.0 km · Goregaon Link RoadRailway line 4.7 km · Western Railway (Slow)Metro station 3.0km away (Valnai-Meeth Chowky)2 bus stops within 500m
Water & environment
Water body 824 m · Gaondevi Lotus TalavRiver 1.1 km · Manori Creek
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Slum Rehabilitation Authority

Slum Rehabilitation Authority
Building Permit
Survey no. C.T.S. No- 524, 524/1 to 16
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Slum Rehabilitation Authority

Planning authority

Has approved 729 RERA projects3.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
554
On record
15,389 flats · 0 plots
Reach
4 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.