01

Complete project overview

MahaRERA · Registration filing
Land area
1,414 sq m
Recreational open space
181 sq m

Timeline

RERA registeredJun 2026
Proposed completionDec 2029
TodaySep 2026
Construction progress
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Excavation100%
Basement (if any)100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

FAITH K S INFRA LLP

Limited Liability PartnershipPromoter type
Mumbai City, MAHARASHTRABased in
1Projects
1City
2026–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kurla
Taluka
Kurla
District
Mumbai Suburban
Pincode
400070
Survey no.
622, 623, 624, 628 & 631
North boundary
CTS No. 632
East boundary
CTS No. 629 & 630
South boundary
Pipe line Road
West boundary
B.M.C Road
What’s nearby
Schools1 school within 500m
HealthcareHospital 231m away · 2 clinics within 1km · Doctor's clinic within 1km
LifestylePark 1.2km away · Gym or sports centre 1.8km away · 6 restaurants and cafes within 1km
ShoppingSupermarket 241m away · Bank 225m away
Getting around
Expressway 604 m · Santa Cruz – Chembur Link RoadPrimary road 537 m · Lal Bahadur Shastri MargRailway line 188 m · Central Railway (Slow)Railway station 355m away (Kurla)Bus stop within 500m
Water & environment
Water body 641 mRiver 782 m · Mithi River
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 622, 623, 624, 628 & 631
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

4,167 residential projects still under way within 25 km. Step out ring by ring:

Of the 2,663 projects the radar draws within 6 km — every kind, every stage — 871 are residential projects still under way. This list keeps only those, and looks further out.

57 projects within 1 km — showing the nearest 6.

100 m awayResidential / Group Housing

PLATINUM SQUARE

N I ENTERPRISES · Kurla

Sep 2025registered
Dec 2027target completion
Scale23 flatsAuthorityMahaRERA
160 m awayResidential / Group Housing

KURLA VIJAY CHS LTD

URBAN BUILD HOMES · Kurla

Feb 2026registered
Dec 2028target completion
Scale20 flatsAuthorityMahaRERA
170 m awayResidential / Group Housing

REHMANIYA APARTMENTS

S & S ENTERPRISES · Kurla

Jan 2025registered
Dec 2026target completion
Scale83 flatsAuthorityMahaRERA
250 m awayMixed

Malad Vrindavan CHSL

Omnetra DB Infra LLP · Malad · Borivali

Aug 2025registered
Dec 2028target completion
Scale58 flatsAuthorityMahaRERA
280 m awayResidential / Group Housing

Rustomjee Vista Bay

Xcellent Realty Private Limited · Parel-Sewree · Mumbai City

Jan 2026registered
Jan 2031target completion
Scale195 flatsAuthorityMahaRERA
340 m awayOthers

SAYBA ELYSIA

SAYBA HOME MAKERS · Kurla

Dec 2024registered
Jul 2027target completion
Scale326 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.