01

Complete project overview

MahaRERA · Registration filing
Project name
FIRDAUS APARTMENTS
Floors
1
Land area
1,382 sq m
Recreational open space
126 sq m

Timeline

RERA registeredJun 2026
Proposed completionMar 2029
TodaySep 2026
Construction progress
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
Basement (if any)30%
Excavation80%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

MAK CORPORATION

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2026–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kurla
Taluka
Kurla
District
Mumbai Suburban
Pincode
400073
Survey no.
822, 822/1 to 4
North boundary
Gr. + 4th floor 1 nos. existing Building) and (Existing chawl)
East boundary
Facing 13.40 mt. wide existing Road.
South boundary
Gr. + 6th floor 1 nos. existing Building
West boundary
Facing 18.30 mt. wide pipe line Road.
What’s nearby
Schools1 school within 500m
HealthcareHospital 350m away · 2 clinics within 1km · Doctor's clinic within 1km
LifestylePark 861m away · 8 restaurants and cafes within 1km
ShoppingSupermarket 420m away · Bank 337m away
Getting around
Expressway 902 m · Santa Cruz – Chembur Link RoadPrimary road 355 m · Lal Bahadur Shastri MargRailway line 168 m · Central Railway (Slow)Railway station 174m away (Kurla)Bus stop within 500m
Water & environment
River 574 m · Mithi RiverWater body 692 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 822, 822/1 to 4
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

4,396 residential and mixed-use projects still under way within 25 km. Step out ring by ring:

Of the 2,707 projects the radar draws within 6 km — every kind, every stage — 941 are residential and mixed-use projects still under way. This list keeps only those, and looks further out.

49 projects within 1 km — showing the nearest 6.

200 m awayResidential / Group Housing

Rustomjee Vista Bay

Xcellent Realty Private Limited · Parel-Sewree · Mumbai City

Jan 2026registered
Jan 2031target completion
Scale195 flatsAuthorityMahaRERA
250 m awayOthers

Kurla Vijay Rahivashi Sangh Co-op. Hsg.Soc.Ltd.

VIKAS NARAYAN RAIKAR · Chembur · Kurla

Apr 2024registered
Dec 2029target completion
AuthorityMahaRERA
250 m awayMixed

Malad Vrindavan CHSL

Omnetra DB Infra LLP · Malad · Borivali

Aug 2025registered
Dec 2028target completion
Scale58 flatsAuthorityMahaRERA
270 m awayResidential / Group Housing

MAJESTIC VISTA

MAJESTIC ROYALE VISMIT INFRAVENTURES LLP · Kurla

Mar 2025registered
Jun 2028target completion
Scale44 flatsAuthorityMahaRERA
270 m awayMixed

Akhand Phase 3

TECHTON LIFESPACES LLP · Gokhiware · Vasai

Jul 2026registered
Dec 2030target completion
Government Guidance Rate₹55,770/sq ydScale546 flatsAuthorityMahaRERA
310 m awayMixed

DAR US SALAM

AIMS INFRA · Kurla

Feb 2026registered
Jun 2029target completion
1 open complaintAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.