Dream Signature

PM1180002502097 · MahaRERA · https://gethorizon.in/projects/dream-signature-oshiwara-andheri-myimqyc6

01

Complete project overview

MahaRERA · Registration filing
Units
556 units
Floors
35
Buildings
2
Parking
326 spaces
Land area
5,940 sq m
Sanctioned built-up
21,405 sq m

Timeline

RERA registeredJan 2026
Proposed completionJun 2030
TodaySep 2026
Construction progress
Excavation0%
Basement (if any)0%
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

Prime Realtors

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
3Projects
3Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
587 homeson the public record across 3 projects
30,123 sq mbuilt-up filed
8,098 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Municipal Corporation of Greater MumbaiMunicipal Corporation1 of 2 projects
Slum Rehabilitation AuthoritySlum Rehabilitation Authoritythis project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from Prime Realtors— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Oshiwara
Taluka
Andheri
District
Mumbai Suburban
Pincode
400102
Survey no.
CTS No. 446/C-2
North boundary
23.80 meter wide Relief Road
East boundary
Building
South boundary
Building
West boundary
13.40 Wide Existing Road
What’s nearby
Schools4 schools within 1km · 5 educational institutions within 1km · Library 961m away
HealthcareHospital 308m away · 8 clinics within 1km · Pharmacy within 500m
LifestylePark 1.6km away · Gym or sports centre 587m away · 54+ restaurants and cafes within 1km
ShoppingSupermarket 473m away · Mall 598m away · Convenience store within 500m
Getting around
Expressway 2.2 kmPrimary road 281 m · Behrambaug RoadRailway line 1.7 km · Central Railway (Harbour Line)Metro station 1m away (Oshiwara)Bus stop within 500m
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Slum Rehabilitation Authority

Slum Rehabilitation Authority
Building Permit
Survey no. CTS No. 446/C-2
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Slum Rehabilitation Authority

Planning authority

Has approved 729 RERA projects3.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
554
On record
15,389 flats · 0 plots
Reach
4 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

3,660 residential projects still under way within 25 km. Step out ring by ring:

Of the 2,152 projects the radar draws within 6 km — every kind, every stage — 740 are residential projects still under way. This list keeps only those, and looks further out.

31 projects within 1 km — showing the nearest 6.

30 m awayOthers

ESQUINA PRIVATE RESIDENCE

PRABHAKAR KUNTE CO OPERATIVE HOUSING SOCIETY LIMITED · Oshiwara · Andheri

Jul 2024registered
Jun 2029target completion
Scale21 flatsAuthorityMahaRERA
360 m awayOthers

Sunbeam Heights

Sun Beam High Tech Developers Private Limited · Oshiwara · Andheri

Mar 2023registered
Dec 2027target completion
Scale322 flatsAuthorityMahaRERA
360 m awayResidential / Group Housing

The Westpark Phase-1

WESTPARK DEVELOPERS PRIVATE LIMITED · Oshiwara · Andheri

Jun 2025registered
Jun 2032target completion
no escrow declaredGovernment Guidance Rate₹1,76,222/sq ydScale416 flatsAuthorityMahaRERA
400 m awayMixed

Gurukrupa Ekam

GURUKRUPA REALCON INFRABUILD LLP · Oshiwara · Andheri

Nov 2025registered
Apr 2029target completion
Government Guidance Rate₹1,76,222/sq ydScale431 flatsAuthorityMahaRERA
510 m awayMixed

Veena Imperia

Veena Infratech LLP · Oshiwara · Andheri

Feb 2026registered
Dec 2030target completion
Scale176 flatsAuthorityMahaRERA
530 m awayResidential / Group Housing

A H Avenue

A.H. Constructions · Andheri

Feb 2022registered
Dec 2026target completion
AuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.