Lodha NCP Tower - 2

P51900046324 · MahaRERA · https://gethorizon.in/projects/lodha-ncp-tower-2-wadala-mumbai-city-8cyvn2w9

01

Complete project overview

MahaRERA · Registration filing
Units
227 units
Floors
45
Buildings
2
Land area
2,226 sq m
Sanctioned built-up
23,676 sq m
Recreational open space
779 sq m

Timeline

RERA registeredJun 2022
Proposed completionMay 2029
TodaySep 2026
Construction progress
Podiums0%
Stilt floor0%
Internal finishes0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Stairs & lifts5%
Superstructure15%
Community Building…70%
Landscaping & Tree…75%
Excavation100%
Basement (if any)100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

LODHA DEVELOPERS LIMITED

CompanyPromoter type
Mumbai City, MAHARASHTRABased in
186Projects
16Cities
2018–presentActive
Timelineevery project, start → promised completion
Lodha AdrinaMhatre CompoundBellissimo Mulund T2UPPER THANE - WOODLANDS A, B AND JLodha Amara Tower 24 and 25Lodha Amara -Tower 42 and 43Lodha Amara Tower 47 and 48Lodha Amara Tower 44UPPER THANE - WOODLANDS C AND DLodha Amara Tower 49 and 50Lodha Belmondo - Tower 30Lodha Belmondo - Tower 32Lodha Bellavista - Wing B2Lodha Pune NIBM ProjectLodha Bellavista - Wing B1Codename One and OnlyLODHA ETERNIS IDYLLIA ALodha Kandivali Project - Tower 5Violet G, H and ILodha Bellagio-Tower CLodha Miraroad Tower - 1 and Tower - 2Lodha NCP Tower - 1Lodha Pune NIBM Project-Tower 6Upper Thane-IRIS Wing ALodha Bellagio-Tower DUpper Thane-Casa EdenLodha MalabarLiana CLodha Pune NIBM Project-Tower 10Lodha Pune NIBM Project-Tower 5Lodha Crown Kolshet-Tower 1Lodha Crown Kolshet-Tower 4Lodha Kandivali Project-Tower 1UPPER THANE-IRIS WING BLodha Pune NIBM Project- Tower 7,8 and 9Liana DMarqLodha Woods - Tower 7Lodha Woods- Tower 8Lodha NCP Tower - 2Lodha Crown Kolshet - Tower 3Lodha Sterling - Tower CFiora G and HCasa BelvedereElanor - Tower 1Elanor - Tower 2Lodha Kolshet A2 - Tower 3Lodha Vikhroli - Tower C1Lodha BellevueBellevue Tower - 3Lodha Villa Royale PalavaLodha Bella Vita SignetLodha Vikhroli-SignetKharadi Pune Phase I - Tower 1 to 4Upper Thane-IRIS Wing CUpper Thane-IRIS Wing DUpper Thane-SupremusKharadi Pune Phase I -Tower 5Lodha Panacea IIICrown Dombivli 1Acenza Tower A and BLodha Crown Kolshet - Tower 2Crown Dombivli 2Bellissimo MatungaKharadi Pune Phase II Tower 7HINJEWADI PROJECTLodha Signet B - KolshetBund Garden ProjectUpper Thane - Eden EHinjewadi Project-Tower 1Hinjewadi Project-Tower 4 and 5Kharadi Pune Phase II -Tower 6Bellissimo Matunga-Tower 2Bellissimo Matunga-Tower 3TulipOlivia Tower -BBelvedere DBelvedere HUpper Thane-IRIS Wing GFiora KUpper Thane-Tiara HFiora JAcenza Tower CLodha MatungaOlivia Tower - AUpper Thane - Tiara GKharadi Pune P2Belvedere-B and CThane ProjectPearlVikhroli ASPI Project 1Upper Thane - Eden DCrown Dombivli 3Vikhroli ASPI Project 3Sea FaceHinjewadi Premium-Tower 7Hinjewadi Premium - Tower 8Lodha Villa Royale TDLR 2Vikhroli ASPI Project 2Kharadi Pune P3Vikhroli Tower C3CullinanPalava -Signet 2WaterviewGolf ViewUpper Thane-Verdura AUpper Thane-Woodlands BCrown Dombivli 4AzurWoods Tower 9Matunga SignetHanging Garden PalavaAltusCorinthia -Tower 1 and Tower 2Kothrud Pune -Tower A and BCorinthia Tower - 5Corinthia-Tower 6Belvedere IForesta EHinjewadi Project-Tower 6Jasper C and DEmerald A and BFiora IAlibaug ProjectBelvedere-KKharadi Pune P1Vikhroli ASPI Project 4Bellissimo Matunga -Tower 4 and Tower 5Azur Tower DBelvedere JAlibaug TownhousesBelvedere EOPULIS COPULIS BOPULIS AOPULIS EAlibaug Residential ProjectOPULIS DKharadi Pune Phase II Tower 8Alibaug PlotsMatunga Wing BKharadi SignetDaffodil K and LPune Wakad ProjectLily A and BLily E and FLily G and HDaffodil A and BLily I and JDaffodil I and JLily K and LDaffodil G and HLily C and DDaffodil M and NDaffodil E and FDaffodil C and DHavenAzur Phase 2Villa ImperioHinjewadi Project-Tower AHinjewadi Project-Tower BLVR Palava -Ready Villa's on landStella-Tower BKharadi New Project - Tower 1Kharadi New Project -Tower 2KHARADI NEW PROJECT -TOWER 4KHARADI NEW PROJECT - TOWER 3KHARADI NEW PROJECT -TOWER 11Hinjewadi Premium - Tower 9Sovrano Tower-BSovrano Tower-ASovrano Tower CLodha ProminaVikhroli Premium Tower A1Hinjewadi Premium - Tower 10KHARADI NEW PROJECT -TOWER 5Lodha Worli Residential ProjectElanzaHaven Phase 2Lodha Sewri ProjectOpulis FAcenza-Tower DAdelphi A and BBelmondo Townhouse 4Casa Supremo RetailFiorana@Beaumont Estate(Phase-1)
Builder DNAthe whole portfolio, summed
33,166 homes · 638 plotson the public record across 186 projects
34,63,747 sq mbuilt-up filed
3,41,118 sq mplotted area
29,14,187 sq mland declared
₹4051.70 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Directorate Of Town Planning & Valuation, Thane46 of 179 projects
Pune Metropolitan Region Development AuthorityMetropolitan Development Authority28 of 179 projects
Municipal Corporation of Greater MumbaiMunicipal Corporation26 of 179 projects
Mumbai Metropolitan Region Development AuthorityMetropolitan Development Authoritythis project20 of 179 projects
Slum Rehabilitation AuthoritySlum Rehabilitation Authority19 of 179 projects
Thane Municipal Corporation , ThaneMunicipal Corporation10 of 179 projects
Thane Municipal CorporationMunicipal Corporation6 of 179 projects
Pune Municipal CorporationMunicipal Corporation5 of 179 projects
BBMP - Bruhat Bengaluru Mahanagara PalikeMunicipal / Corporation3 of 179 projects
BDA - Bangalore Development AuthorityUrban Development Authority2 of 179 projects
Directorate Of Town Planning & Valuation, Alibaug, Raigad2 of 179 projects
Thane Municipal Corporation ThaneMunicipal Corporation2 of 179 projects
Anekal Planning AuthorityTown & Country Planning (DTCP)1 of 179 projects
BIAPPA - Bangalore Airport Area Planning AuthorityUrban Development Authority1 of 179 projects
Ce/9233/Ws/Ak/Fcc/9/Amend1 of 179 projects
Directorate Of Town Planning And Valuation1 of 179 projects
Mira Bhayandar Municipal CorporationMunicipal Corporation1 of 179 projects
Mira Bhayandar Municipal Corporation,ThaneMunicipal Corporation1 of 179 projects
P 11910/2022/(1913)/E Ward/Byculla/Fcc/3/Amend1 of 179 projects
Pimpri Chinchwad Municipal CorporationMunicipal Corporation1 of 179 projects
Pune Municipla Corporation1 of 179 projects
The Assistant Director Of Town Planning1 of 179 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from LODHA DEVELOPERS LIMITED— the full portfolio →

03

Location

MahaRERA · Registration filing
District
Mumbai City
Pincode
400022
Survey no.
BLOCK C, WTT, CS. NO 8 pt Saltpan Division
North boundary
RG and Commercial Building
East boundary
36 point 58 m wide Existing Road
South boundary
RG and Clubhouse
West boundary
RG and Lodha Estrella D7 and E9
What’s nearby
SchoolsNearest school 1.3km away · College or university 1.1km away · Library 667m away
HealthcareHospital 422m away · 2 clinics within 1km
LifestylePark 502m away
ShoppingSupermarket 1.7km away · Mall 1.9km away · Bank 844m away
Getting around
Expressway 1.5 km · King's CirclePrimary road 249 mRailway line 413 mRailway station 544m away (Wadala Bridge)Limited bus connectivity nearby
Water & environment
Water body 639 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Mumbai Metropolitan Region Development Authority

Metropolitan Development Authority
Building Permit
Survey no. BLOCK C, WTT, CS. NO 8 pt Saltpan Division
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Mumbai Metropolitan Region Development Authority

Metropolitan / development authority

Has approved 152 RERA projects0.8% of Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
93
On record
7,406 flats · 157 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

3,541 residential projects still under way within 25 km. Step out ring by ring:

Of the 1,398 projects the radar draws within 6 km — every kind, every stage — 470 are residential projects still under way. This list keeps only those, and looks further out.

11 projects within 1 km — showing the nearest 6.

WadalaResidential / Group Housing

Lodha NCP Tower - 1

LODHA DEVELOPERS LIMITED

Mar 2022registered
Dec 2026target completion
Scale225 flatsAuthorityMahaRERA
Mumbai CityResidential / Group Housing

Labdhi Seabreeze

Labdhi Siddhivinayak Realtors LLP

Jan 2020registered
Dec 2027target completion
2 open complaintsScale268 flatsAuthorityMahaRERA
Fnorth-400019Residential / Group Housing

Godrej Horizon Phase I

Godrej Projects Development Ltd

Apr 2022registered
May 2028target completion
2 open complaintsScale400 flatsAuthorityMahaRERA
WadalaResidential / Group Housing

Godrej Horizon Phase II

Godrej Projects Development Ltd

Feb 2023registered
Jun 2029target completion
1 open complaintScale352 flatsAuthorityMahaRERA
WADALA EASTResidential / Group Housing

DOSTI EASTERN BAY - PHASE 1

DOSTI REALTY LTD

Mar 2020registered
Mar 2028target completion
Scale422 flatsAuthorityMahaRERA
WADALA EASTResidential / Group Housing

DOSTI EASTERN BAY- PHASE 2

DOSTI REALTY LTD

Sep 2021registered
Sep 2027target completion
Scale170 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.