HORIZONMarkets
01

Complete project overview

RERA Karnataka · Registration filing
Status
Ongoing
Plots
247 plots
Land parcels
9 survey nos

Timeline

Project startedAug 2025
RERA registeredOct 2025
Proposed completionDec 2028
TodayJul 2026
Construction progress

73% overall, as filed

From the promoter's latest quarterly progress report filed with RERA Karnataka — % complete overall and by stage, as of that filing. A dated snapshot, not a live tracker.

Find your plot

Every plot the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.

UnitTypeTotal sq m
1Plot240.12
2Plot150.94
3Plot149.42
4Plot147.90
5Plot130.66
6Plot140.07
7Plot115.79
8Plot119.50
9Plot129.83
10Plot120.94
11Plot135.45
12Plot203.23
13Plot229.04
14Plot228.83
15Plot238.84
16Plot168.01
17Plot139.29
18Plot139.29
19Plot139.29
20Plot139.29
21Plot139.29
22Plot139.29
23Plot151.75
24Plot176.68
25Plot139.29
26Plot139.29
27Plot139.29
28Plot139.29
29Plot139.29
30Plot139.29
31Plot116.68
32Plot254.02
33Plot139.29
34Plot139.29
35Plot139.29
36Plot139.29
37Plot139.29
38Plot151.75
39Plot151.75
40Plot139.29
41Plot139.29
42Plot139.29
43Plot139.29
44Plot139.29
45Plot209.43
46Plot147.78
47Plot111.42
48Plot111.42
49Plot111.42
50Plot111.42
51Plot111.42
52Plot169.78
53Plot126.19
54Plot111.42
55Plot111.42
56Plot111.42
57Plot111.42
58Plot111.42
59Plot111.42
60Plot111.42
61Plot147.78
62Plot155.79
63Plot111.42
64Plot111.42
65Plot111.42
66Plot111.42
67Plot111.42
68Plot111.42
69Plot111.42
70Plot111.42
71Plot111.42
72Plot111.42
73Plot111.42
74Plot111.42
75Plot111.42
76Plot111.42
77Plot111.42
78Plot111.42
79Plot155.79
80Plot78.86
81Plot111.42
82Plot111.42
83Plot111.42
84Plot111.42
85Plot147.78
86Plot111.42
87Plot111.42
88Plot111.42
89Plot111.42
90Plot111.42
91Plot111.42
92Plot111.42
93Plot111.42
94Plot111.42
95Plot111.42
96Plot111.42
97Plot111.42
98Plot111.42
99Plot111.42
100Plot111.42
101Plot111.42
102Plot105.49
103Plot103.46
104Plot149.27
105Plot111.42
106Plot111.42
107Plot111.42
108Plot111.42
109Plot111.42
110Plot111.42
111Plot111.42
112Plot111.42
113Plot111.42
114Plot111.42
115Plot111.42
116Plot111.42
117Plot111.42
118Plot111.42
119Plot111.42
120Plot111.42
121Plot111.42
122Plot147.78
123Plot111.42
124Plot111.42
125Plot111.42
126Plot111.42
127Plot88.28
128Plot104.66
129Plot111.42
130Plot111.42
131Plot111.42
132Plot111.42
133Plot111.42
134Plot111.42
135Plot111.42
136Plot111.42
137Plot111.42
138Plot111.42
139Plot111.42
140Plot111.42
141Plot111.42
142Plot111.42
143Plot111.42
144Plot111.42
145Plot111.42
146Plot111.42
147Plot111.42
148Plot111.42
149Plot111.42
150Plot111.42
151Plot149.91
152Plot129.29
153Plot111.42
154Plot111.42
155Plot111.42
156Plot111.42
157Plot111.42
158Plot111.42
159Plot111.42
160Plot111.42
161Plot111.42
162Plot111.42
163Plot111.42
164Plot111.42
165Plot111.42
166Plot111.42
167Plot111.42
168Plot111.42
169Plot111.42
170Plot111.42
171Plot111.42
172Plot111.42
173Plot111.42
174Plot111.42
175Plot114.09
176Plot185.36
177Plot192.74
178Plot149.87
179Plot111.42
180Plot111.42
181Plot111.42
182Plot111.42
183Plot111.42
184Plot111.42
185Plot111.42
186Plot111.42
187Plot111.42
188Plot111.42
189Plot111.42
190Plot111.42
191Plot111.42
192Plot111.42
193Plot111.42
194Plot111.42
195Plot95.03
196Plot185.83
197Plot111.42
198Plot111.42
199Plot111.42
200Plot111.42
201Plot111.42
202Plot111.42
203Plot111.42
204Plot111.42
205Plot111.42
206Plot111.42
207Plot111.42
208Plot111.42
209Plot111.42
210Plot137.02
211Plot111.42
212Plot127.23
213Plot154.12
214Plot111.42
215Plot157.64
216Plot146.35
217Plot111.42
218Plot111.42
219Plot136.58
220Plot163.48
221Plot111.42
222Plot111.42
223Plot166.97
224Plot105.72
225Plot109.90
226Plot113.27
227Plot115.87
228Plot118.40
229Plot120.92
230Plot123.45
231Plot125.97
232Plot128.49
233Plot131.02
234Plot133.54
235Plot146.31
236Plot141.54
237Plot139.29
238Plot139.29
239Plot139.29
240Plot139.29
241Plot139.29
242Plot139.29
243Plot139.29
244Plot139.29
245Plot139.29
246Plot139.29
247Plot116.35

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion.

02

Builder’s track record

RERA Karnataka · Promoter registration

Manyata Developers Pvt Ltd

CompanyPromoter type
Bengaluru UrbanBased in
6Projects
2Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
617 plotson the public record across 6 projects
2,23,635 sq mplotted area
2,23,635 sq mland declared
₹304.64 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
BIAPPA - Bangalore Airport Area Planning AuthorityUrban Development Authority4 of 6 projects
Anekal Planning AuthorityTown & Country Planning (DTCP)this project1 of 6 projects
Local Planning AuthorityTown & Country Planning (DTCP)1 of 6 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Anekal
District
Bengaluru Urban
Pincode
562125
Address
SY. NO. 111/1A, 111/1B, 111/2(P), 113(P), 114, 122/2, 169/1(P) & 169/2 OF NERIGA VILLAGE , SARJAPURA HOBLI , Anekal , Bengaluru Urban, Karnataka - 562125
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.8km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 4.7 km · Dabaspete - Hosur HighwayPrimary road 3.2 km · Varthur - Sarjapur RoadNo metro or railway within 5kmBus stop within 1km
Water & environment
Water body 623 m · Neriga Lake
distances only — not a flood assessment
Land, title & encumbrance
LandOwned by the promoter
ConversionConverted to non-agricultural
LitigationDeclared free of litigation
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹53.05 Cr declared to build 247 plots. What that works out to:

₹21.48 Lakhdeclared cost per plotall-in — land + construction
58%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

Anekal Planning Authority

Town & Country Planning (DTCP)
approved 26 Aug 2020 · 5 yrs ago
Layout Permit no. AYOPRA:LAO:68:2018-19Survey no. 111-1b
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan AYOPRA:LAO:68:2018-19 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Anekal Planning Authority

Town & Country Planning

Has approved 64 RERA projects0.7% of Karnataka.

a mixed market56% apartments · 44% plotted layouts.

Builders
56
On record
7,036 flats · 3,053 plots
Reach
3 taluks
Since
2025

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

None on record with RERA Karnataka against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.