HORIZON
Share

NEW KANDIVALI CHSL

P51800077407 · MahaRERA · https://gethorizon.in/projects/new-kandivali-chsl-malad-borivali-hmd1hhkb

01

Complete project overview

MahaRERA · Registration filing
Units
31 units
Floors
8
Buildings
2
Parking
35 spaces
Land area
851 sq m
Sanctioned built-up
1,925 sq m

Timeline

RERA registeredAug 2024
Proposed completionDec 2026
TodaySep 2026
Construction progress
Podiums0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
OC-readiness50%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

KAMPA PROJECTS LLP

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
2Projects
1City
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
31 homeson the public record across 2 projects
4,936 sq mbuilt-up filed
2,017 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from KAMPA PROJECTS LLP— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Malad
Taluka
Borivali
District
Mumbai Suburban
Pincode
400067
Survey no.
77, 77/1 to 4
North boundary
by adjoing cts no 76
East boundary
by adjoining cts no 73
South boundary
by adjoining cts no 78
West boundary
by existing devji bhimji road
What’s nearby
SchoolsNearest school 1.1km away · College or university 361m away
HealthcareHospital 36m away · 10 clinics within 1km · Pharmacy within 500m
LifestylePark 1.1km away · Gym or sports centre 1.7km away · 11+ restaurants and cafes within 1km
ShoppingSupermarket 1.3km away · Mall 1.5km away · Bank 73m away
Getting around
Expressway 1.3 km · Western Express HighwayPrimary road 35 m · Swami Vivekanand RoadRailway line 285 m · Western Railway Virar to BorivaliRailway station 254m away (Kandivali)Bus stop within 500m
Water & environment
Water body 1.0 km
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 77, 77/1 to 4
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

3,922 residential projects still under way within 25 km. Step out ring by ring:

Of the 2,149 projects the radar draws within 6 km — every kind, every stage — 741 are residential projects still under way. This list keeps only those, and looks further out.

48 projects within 1 km — showing the nearest 6.

70 m awayOthers

VENCON BHAGAT NIWAS

VENCON REALTY AND INFRASTRUCTURE LLP · Poisar · Borivali

May 2025registered
Dec 2027target completion
Government Guidance Rate₹1,34,123/sq ydScale65 flatsAuthorityMahaRERA
200 m awayResidential / Group Housing

MODERN ROOP-KAMAL CO-OPERATIVE HOUSING SOCIETY LTD

Konark Structural Engineers Private Limited · Poisar · Borivali

Oct 2025registered
Dec 2029target completion
Government Guidance Rate₹1,11,397/sq ydScale66 flatsAuthorityMahaRERA
210 m awayResidential / Group Housing

Swastik House - C Wing

SWASTIK CONSTRUCTIONS · Poisar · Borivali

Aug 2024registered
Mar 2030target completion
Government Guidance Rate₹1,34,123/sq ydScale28 flatsAuthorityMahaRERA
230 m awayResidential / Group Housing

MEENA HOUSE

RAMESH R PAREKH HUF · Malad · Borivali

Apr 2024registered
Mar 2027target completion
AuthorityMahaRERA
240 m awayOthers

Shelton Aspire

Shelton Infra Projects Private Limited · Malad · Borivali

May 2025registered
Mar 2028target completion
Government Guidance Rate₹1,35,210/sq ydScale35 flatsAuthorityMahaRERA
280 m awayResidential / Group Housing

SHREEJI SKY RISE TOWER

Shreeji Construction · Borivali

Dec 2021registered
Dec 2026target completion
Scale237 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.