Complete project overview

MahaRERA · Registration filing
Floors
23
Buildings
2
Parking
166 spaces
Land area
772 sq m
Sanctioned built-up
6,206 sq m

Timeline

RERA registeredMay 2024
Proposed completionMar 2029
TodayJul 2026
Construction progress
Podiums0%
Flat fit-out0%
OC-readiness0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
External finishes13%
Water Supply35%
Internal finishes40%
Stairs & lifts90%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

RADHA KRISHNA ENTERPRISES

PartnershipPromoter type
Palghar, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Vasai-Virar City (M Corp)
Taluka
Vasai
District
Palghar
Pincode
401208
Survey no.
SURVEY NO 85, HISSA NO 10
North boundary
Plot Boundry
East boundary
Plot Boundry
South boundary
Building No 13
West boundary
15 Meters Wide Road
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.4km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 3.9 km · Mumbai Delhi HighwayPrimary road 714 m · Vasai RoadRailway line 1.7 kmRailway station 1.8km away (Vasai Road)Bus stop within 1km
Water & environment
River 551 mWater body 583 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Vasai Virar City Municipal Corporation

Municipal Corporation
Building Permit
Survey no. SURVEY NO 85, HISSA NO 10
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Vasai Virar City Municipal Corporation

Municipal corporation

Has approved 627 RERA projects3.1% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
513
On record
8,010 flats · 60 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.