Complete project overview

GujRERA · Registration filing
Units
85 units
Mix
85 × 85
Carpet area
21–78 sq mper-unit range, as filed
Parking
4 spaces
Land area
1,539 sq m
Affordable housing
Yes — registered under affordable housingprice caps & eligibility apply

Timeline

Project startedSep 2022
RERA registeredJan 2023
Proposed completionDec 2026
TodaySep 2026
Construction progress

55% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your unit

Filed by type and size, in the batches the builder registered — not a per-unit listing. Look yours up.

85 units across 1 batch
TypeArea sq mCount
855885

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Builder registration

SIDDHI DEVELOPERS

PARTNERSHIP FIRMPromoter type
Vadodara, GujaratBased in
18Projects
13Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,133 homeson the public record across 18 projects
48,572 sq mbuilt-up filed
49,382 sq mland declared
₹268.03 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporation2 of 13 projects
Vadodara Municipal CorporationMunicipal / Corporation2 of 13 projects
Ahmedabad Urban Development AuthorityUrban Development Authority1 of 13 projects
Bilimora MunicipalityMunicipal / Corporation1 of 13 projects
Chhatrapati Sambhajinagar Municipal Corporation, Chhatrapati SambhajinagarMunicipal Corporation1 of 13 projects
District Magistrate Office Thane1 of 13 projects
Mira Bhayander Municipal CorporationMunicipal Corporation1 of 13 projects
Nashik Metropolitian Region Development Authority NashikMetropolitan Development Authority1 of 13 projects
Nashik Municipal CorporationMunicipal Corporation1 of 13 projects
Navsari Urban Development AuthorityUrban Development Authority1 of 13 projects
Othersthis project1 of 13 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from SIDDHI DEVELOPERS— the full portfolio →

03

Location & price analysis

GujRERA · Registration filing
Taluka
Vadodara
District
Vadodara
Address
TRINETRA SKYDECK NR. KHISKOLI CIRCLEMANJALPUR-ATLADRA ROAD
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 672m away · Clinic within 2km
LifestyleNo parks within 2km · Gym or sports centre 1.5km away
ShoppingNo supermarket within 2km
Getting around
Expressway 3.0 km · Lalbagh FlyoverPrimary road 423 mRailway line 1.1 km · Mumbai - Delhi RailwayRailway station 1.5km away (Atladara)Limited bus connectivity nearby
Water & environment
River 315 m · Vishwamitri RiverWater body 1.9 km
distances only — not a flood assessment
Land, title & encumbrance
Mortgage85 unit(s) mortgaged to IIFL HOME FINANCE · ₹3.16 Cr outstanding
As declared by the builder at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹15.80 Cr declared to build 85 flats. What that works out to:

₹20.00 Lakh – ₹40.00 Lakhdeclared unit pricerange on the filing — not a live asking price
₹18.59 Lakhdeclared cost per flatall-in — land + construction
₹2,970/sq ftof carpet area₹31,969/sq m
22%of the cost is land₹2,070/sq ft of land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Gujarat Revenue Department — Annual Statement of Rates (jantri), 2011

In Gujarat it’s called the jantri rate — the 2011 book, which is the one in Horizon's record.

₹9,197per sq yd
₹11,000per sq m
Which rate
land + construction: residential flat
Matched to
The rate published for the village of “ATLADRA”.
In force
2011 schedule

This filing declares ₹31,969 per sq m of carpet area — 2.91× the government figure. Declared cost is land and construction; the government guidance rate is what the state will not register a sale below. Neither is a sale price.

What this number is — and isn’t

  • The minimum value Gujarat’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

GujRERA · Approved building plan

Others

Building Permitapproved 5 Jan 2023 · 3 yrs ago
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

The approving authority

The body that approved this project. It has approved 2,653 RERA projects across 26 talukas about 1 in 6 in Gujarat.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

1,154 residential projects still under way within 25 km. Step out ring by ring:

Of the 1,404 projects the radar draws within 6 km — every kind, every stage — 533 are residential projects still under way. This list keeps only those, and looks further out.

14 projects within 1 km — showing the nearest 6.

70 m awayMixed Development

SAMRUDDHI SILVER

SAMRUDDHI SILVER · Vadodara

Nov 2022registered
Dec 2027target completion
Declared cost₹29.80 CrScale181 flatsAuthorityGujRERA
130 m awayMixed Development

SOHAM RESICOM

KANKESHWARI DEVELOPERS · Vadodara

Mar 2023registered
Dec 2027target completion
Declared cost₹9.66 CrScale65 flatsAuthorityGujRERA
400 m awayMixed Development

PMAY, EWS, TP 28, FP 152/1+152/2, R.S.no.585/1 ATLADRA

VADODARA MUNICIPAL CORPORATION · Vadodara

May 2022registered
Dec 2027target completion
Declared cost₹166.76 CrScale1,980 flatsAuthorityGujRERA
570 m awayResidential/Group Housing

SHANTAM VILLA

STONE CRAFT INFRA · Vadodara

Apr 2023registered
Sep 2026target completion
Declared cost₹21.04 CrScale25 flatsAuthorityGujRERA
580 m awayMixed Development

SHREE SIDDHESHWAR HELICON

N K PLUS · Vadodara

Jul 2024registered
Apr 2029target completion
Price band₹15.25 Lakh–₹49.50 LakhScale372 flatsAuthorityGujRERA
610 m awayResidential/Group Housing

Auro Opulent

SHREEJI SHARAN · Vadodara

Dec 2025registered
Dec 2031target completion
Price band₹1.10 Cr–₹1.10 CrScale17 flatsAuthorityGujRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.