SILVER HOMES

UPRERAPRJ12399 · UP-RERA · https://gethorizon.in/projects/silver-homes-ghaziabad-pt9adz0q

01

Complete project overview

UP-RERA · Registration filing
Project name
SILVER HOMES
Land area
3,542 sq m

Timeline

Project startedOct 2015
RERA registeredAug 2017
Proposed completionDec 2022
TodaySep 2026
02

Builder’s track record

UP-RERA · Builder registration

RATANDEEP INFRASTRUCTURE PVT. LTD.

CompanyPromoter type
1Registered projects
1Projects
1City
2017–2022Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Ghaziabad
Tehsil
Ghaziabad
Site access
On 24 Meter Wide Road
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 434m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 310 mRailway line 1.4 kmRailway station 4.4km away (Naya Ghaziabad)Limited bus connectivity nearby
Water & environment
Water body 1.1 kmCanal 1.9 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹3.00 Cr declared. What that works out to:

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Uttar Pradesh registration department

In Uttar Pradesh it’s called the circle rate.

No government guidance rate is shown for this project.

Uttar Pradesh's government guidance rates aren't in Horizon's record yet.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

UP-RERA · Approved building plan
Building Permit

The promised possession date (29 Dec 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

07

Other projects nearby

The register · within 25 km

173 residential projects still under way within 25 km. Step out ring by ring:

Of the 253 projects the radar draws within 6 km — every kind, every stage — 38 are residential projects still under way. This list keeps only those, and looks further out.

4 projects within 1 km — showing the nearest 4.

230 m awayResidential

Flora Homez

AKJ REAL TECH PRIVATE LIMITED · Ghaziabad

Jul 2026registered
Jan 2031target completion
no escrow declaredDeclared cost₹101.00 CrScale124 flatsAuthorityUP-RERA
390 m awayResidential

AIGIN ROYAL PARK

AIG BUILDCON PRIVATE LIMITED; UTILITY ESTATES PRIVATE LIMITED · Ghaziabad

Jul 2023registered
May 2029target completion
no escrow declaredDeclared cost₹203.30 CrScale263 flatsAuthorityUP-RERA
540 m awayResidential

Floral Pathways

ATS GRAND REALTORS PRIVATE LIMITED; VOYAGE REAL ESTATES PRIVATE LIMITED · Ghaziabad

Jun 2021registered
Apr 2027target completion
Declared cost₹532.49 CrScale788 flatsAuthorityUP-RERA
700 m awayResidential

Rosemont Residency - (Phase-01)

PARK TOWN COMPLEX PRIVATE LIMITED; ROSEMONT RESIDENCES PRIVATE LIMITED · Ghaziabad

May 2026registered
Feb 2031target completion
no escrow declaredDeclared cost₹513.00 CrScale455 flatsAuthorityUP-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.