SAI PALACE

PM1330002600063 · MahaRERA · https://gethorizon.in/projects/sai-palace-thane-m-corp-xcjlkj66

01

Complete project overview

MahaRERA · Registration filing
Units
50 units
Floors
8
Buildings
4
Parking
58 spaces
Land area
742 sq m
Sanctioned built-up
2,517 sq m

Timeline

RERA registeredApr 2026
Proposed completionAug 2029
TodaySep 2026
Construction progress
Excavation0%
Basement (if any)0%
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

SAI ENTERPRISES

PartnershipPromoter type
Thane, MAHARASHTRABased in
11Projects
9Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
787 homes · 37 plotson the public record across 11 projects
17,535 sq mbuilt-up filed
13,000 sq mplotted area
29,871 sq mland declared
₹8.68 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from SAI ENTERPRISES— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400605
Survey no.
plot_no - city_survey_gut_no 497/A/3 final_plot_no - sector_no 8 mauje Kalwa road_street 6.00 M. society VINAYAKI CHS
North boundary
GANESH BHAWAN
East boundary
SALVI NIWAS/6 MTRS INTERNAL ROAD
South boundary
SAI JANKI SADAN
West boundary
VIGHNAHAR SOCIETY
What’s nearby
Schools1 school within 500m · College or university 1.3km away · Library 1.6km away
HealthcareHospital 61m away · 1 clinic within 1km · Pharmacy within 500m
LifestylePark 1.8km away · Gym or sports centre 1.4km away
ShoppingNo supermarket within 2km
Getting around
Expressway 1.5 km · Eastern Express HighwayPrimary road 368 m · Kalwa NakaRailway line 460 mRailway station 576m away (Kalva)8 bus stops within 500m
Water & environment
Water body 570 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹60,034per sq yd
₹71,800per sq m
Which rate
residential flat (built)
Matched to
The middle rate across the 101 divisions of “Thane (M Corp.)” — the city's middle, not this project's own division.
In force
2026-2027 schedule
Spread
₹26,923₹1,55,185 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of city, and says so above. How Horizon decides what to show.
06

Other projects nearby

The register · within 25 km

4,846 residential projects still under way within 25 km. Step out ring by ring:

Of the 1,589 projects the radar draws within 6 km — every kind, every stage — 542 are residential projects still under way. This list keeps only those, and looks further out.

7 projects within 1 km — showing the nearest 6.

60 m awayOthers

ASHAR ARIZE N.M.M. SOCIETY TOWER A

Ms ASHAR VENTURES · Thane

Apr 2022registered
Jan 2027target completion
Government Guidance Rate₹60,034/sq ydScale396 flatsAuthorityMahaRERA
150 m awayResidential / Group Housing

SHREE SAI CHARAN CHSL

MANDAR CONSTRUCTIONS AND DEVELOPERS LLP · Thane

Nov 2025registered
May 2029target completion
Government Guidance Rate₹60,034/sq ydScale114 flatsAuthorityMahaRERA
220 m awayResidential / Group Housing

SUNSHINE

M/S SIDDHIVINAYAK DEVELOPERS · Thane

May 2024registered
Dec 2028target completion
Government Guidance Rate₹60,034/sq ydScale24 flatsAuthorityMahaRERA
260 m awayResidential / Group Housing

AMOL SAUBHAGYA

SUMAN REALTIES · Kalwa · Thane

Mar 2026registered
Mar 2028target completion
Government Guidance Rate₹72,743/sq ydScale54 flatsAuthorityMahaRERA
390 m awayResidential / Group Housing

GAONDEVI ARCADE

TABISH ZAID CHEULKAR · Thane

Feb 2025registered
Jul 2027target completion
Government Guidance Rate₹60,034/sq ydScale39 flatsAuthorityMahaRERA
770 m awayResidential / Group Housing

Birla Taranya - Phase 1

Ekamaya Properties Private Limited · Kalwa · Thane

Feb 2026registered
Mar 2032target completion
Government Guidance Rate₹72,743/sq ydScale1,339 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.