Project name
VRR Golden Enclave Phase – I
Towers
1
Land area
28,328 sq m
FAR sanctioned
2.25
Covered area
12,267 sq m
Open area
3,760 sq m

Timeline

Project startedSep 2016
RERA registeredMar 2019
Proposed completionAug 2019
TodaySep 2026

Find your flat

Every flat the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.

UnitTypeCarpet sq mExclusive area sq mUndivided share sq m
A-12Ground Floor3BHK262.90101.50326.79
A-13Ground Floor3BHK262.90101.50321.02
A-14Ground Floor3BHK262.90101.50326.79
A-15Ground Floor3BHK262.90101.50321.02
A-16Ground Floor3BHK262.90101.50326.79
A-17Ground Floor3BHK262.90101.50321.02
A-18Ground Floor3BHK265.50101.50327.22
A-19Ground Floor3BHK265.50101.50326.87
A-20Ground Floor3BHK265.50101.50327.22
A-21Ground Floor3BHK265.50101.50326.87
A-22Ground Floor3BHK265.50101.50327.22
A-23Ground Floor3BHK265.50101.50326.87
B-12Ground Floor3BHK262.90101.50326.79
B-13Ground Floor3BHK262.90101.50321.02
B-14Ground Floor3BHK262.90101.50326.79
B-15Ground Floor3BHK262.90101.50321.02
B-16Ground Floor3BHK262.90101.50326.79
B-17Ground Floor3BHK262.90101.50321.02
B-18Ground Floor3BHK265.50101.50327.22
B-19Ground Floor3BHK265.50101.50326.87
B-20Ground Floor3BHK265.50101.50327.22
B-21Ground Floor3BHK265.50101.50326.87
B-22Ground Floor3BHK265.50101.50327.22
B-23Ground Floor3BHK265.50101.50326.87
C-13Ground Floor3BHK262.90101.50321.02
C-14Ground Floor3BHK262.90101.50326.79
C-15Ground Floor3BHK262.90101.50321.02
C-16Ground Floor3BHK262.90101.50326.79
C-17Ground Floor3BHK262.90101.50321.02
C-18Ground Floor3BHK262.90101.50328.79

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. Carpet area is the legally meaningful number — not the super built-up figure a brochure quotes. Exclusive area is the common area allotted exclusively to the unit's owner, as the register names it. Undivided share is the portion of the land that comes with the unit, as filed — a share of the whole plot, not a demarcated piece of ground.

02

Builder’s track record

RERA Karnataka · Builder registration

H. N. Vijaya Raghava Reddy & Co.

Bengaluru UrbanBased in
2Projects
2Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects
39,962 sq mland declared
₹394.36 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
BBMP - Bruhat Bengaluru Mahanagara PalikeMunicipal / Corporation1 of 2 projects
BDA - Bangalore Development AuthorityUrban Development Authoritythis project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from H. N. Vijaya Raghava Reddy & Co.— the full portfolio →

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Anekal
District
Bengaluru Urban
Pincode
560095
Address
Sy. No.355, Old Sy. No.155/14, Hulimangala Village, Jigani Hobli, Anekal Taluk
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.3km away · Clinic within 2km
LifestylePark 969m away
ShoppingSupermarket 1.3km away
Getting around
Expressway 3.7 km · Hosur RoadPrimary road 3.9 km · Bannerghatta Main RoadMetro station 3.7km away (Biocon Hebbagodi)Limited bus connectivity nearby
Water & environment
Water body 586 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹128.00 Cr declared. What that works out to:

46%of the cost is land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Karnataka registration department

In Karnataka it’s called the guidance value.

No government guidance rate is shown for this project.

Karnataka's guidance-value gazettes are in Horizon's record, but this project's address doesn't name a place any of its sub-registrar's tables print.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

RERA Karnataka · Approved building plan

BDA - Bangalore Development Authority

Urban Development Authority
Building Permit

The promised possession date (10 Aug 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

BDA

Urban Development Authority · Bangalore Development Authority

Has approved 830 RERA projectsabout 1 in 11 in Karnataka.

an apartments market73% apartments · 27% plotted layouts. Apartments like yours are this body's core business.

Builders
626
On record
82,843 flats · 16,515 plots
Reach
13 taluks
Since
2017

More apartment-heavy than Karnataka overall — 73% apartments here vs 62% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by RERA Karnataka

07

Other projects nearby

The register · within 25 km

778 residential projects still under way within 25 km. Step out ring by ring:

Of the 238 projects the radar draws within 6 km — every kind, every stage — 65 are residential projects still under way. This list keeps only those, and looks further out.

6 projects within 1 km — showing the nearest 6.

380 m awayApartment

M5 ECHELON

Mahendra Homes Private Limited · Anekal

Jul 2026started
Dec 2031target completion
Declared cost₹832.99 CrScale795 flatsAuthorityRERA Karnataka
550 m awayVilla

VILLA BELLISSIMO

URBANIZE LAND HOLDINGS PRIVATE LIMITED · Anekal

Dec 2023started
Dec 2028target completion
Declared cost₹145.65 CrScale103 flatsAuthorityRERA Karnataka
640 m awayRow Houses

VRR GOLDEN ENCLAVE PHASE-III

H.N.VIJAYARAGHAVA REDDY CO · Anekal

Nov 2024started
Jun 2027target completion
Declared cost₹22.53 CrScale13 flatsAuthorityRERA Karnataka
640 m awayVilla

VRR GOLDEN ENCLAVE PHASE II

H N VIJAYARAGHAVA REDDY CO · Anekal

Aug 2021started
Dec 2027target completion
Declared cost₹82.29 CrScale84 flatsAuthorityRERA Karnataka
800 m awayResidential/Group Housing

SRIKARA URBAN PARK

SRIKARA STRUCTURES · Anekal

Mar 2021started
Mar 2026target completion
no escrow declaredDeclared cost₹28.74 CrAuthorityRERA Karnataka
890 m awayApartment

Habulus Oasis Grove

HABULUS HOMES PRIVATE LIMITED · Anekal

Mar 2026started
Mar 2031target completion
Declared cost₹162.36 CrScale296 flatsAuthorityRERA Karnataka

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.