SPL PALMS DEVELOPERS PRIVATE LIMITED · Bengaluru North
SHRIRAM SUVILAS GARDEN OF JOY
Timeline
Every flat the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. Carpet area is the legally meaningful number — not the super built-up figure a brochure quotes. Exclusive area is the common area allotted exclusively to the unit's owner, as the register names it.
The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
₹60.55 Cr declared. What that works out to:
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
In Karnataka it’s called the guidance value.
No government guidance rate is shown for this project.
Karnataka's guidance-value gazettes are in Horizon's record, but this project's address doesn't name a place any of its sub-registrar's tables print.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
The promised possession date (1 Jul 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
Has approved 2,111 RERA projects — about 1 in 4 in Karnataka, more than any other body in the state.
an apartments market — 100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.
More apartment-heavy than Karnataka overall — 100% apartments here vs 62% statewide.
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
12 complaints · 12 disposed · 0 open
A disposed complaint may have been resolved for or against the builder, and only disputes escalated to RERA Karnataka appear here at all.
| Number | Date | Status | |
|---|---|---|---|
| 00153/2023 | Return of amount (rs. 4053630 plus other expenses for flat [no.].07.08) along with interest or compensation as per sale agreement in case of dealy from builder/promoter-reg | 2 Feb 2023 | Disposed — authority bench 6 |
| 00148/2023 | Project is stalled, Delivery date is expired and No compensation given for the expiry | 1 Feb 2023 | Disposed — authority bench 6 |
| 00101/2023 | Delivery date expired and project stalled. Project not completed and asking for extension without compensation. Full refund and compensation for financial and mental distress imposed on me by builder. | 19 Jan 2023 | Disposed — authority bench 6 |
| 00050/2023 | Refund of the amount paid along with Interest for the Apartment Flat booking | 10 Jan 2023 | Disposed — authority bench 6 |
| CMP/221125/0010404 | Project construction Delayed and stalled | 25 Nov 2022 | Disposed — authority bench 6 |
| Number | Date | Status | |
|---|---|---|---|
| CMP/221115/0010339 | Refund of All Amount Paid against FLAT | 15 Nov 2022 | Disposed — authority bench 6 |
| CMP/221102/0010156 | Complaint to claim a full refund and compensation for financial and mental distress imposed on me by the builder | 2 Nov 2022 | Disposed — authority bench 6 |
| CMP/221029/0010151 | Delayed Completion of the Project - Shriram Suvilas Garden of Joy Jalahalli | 29 Oct 2022 | Disposed — authority bench 6 |
| CMP/220903/0009974 | Project not completed and Asking for extension without compensation | 3 Sep 2022 | Disposed — authority bench 5 |
| CMP/220623/0009670 | Return of full paid amount (Rs. 41,06,340/-) along with interest for Unit [no.].02.04 as Builder failed to complete the project as per agreed timeline (Oct 2022) | 23 Jun 2022 | Disposed — authority bench 6 |
| CMP/220516/0009461 | Delivery date expiry | 16 May 2022 | Disposed — authority bench 6 |
| CMP/220223/0009046 | Request for refund for Unit [no.]-07-04 Shriram Garden of Joy | 23 Feb 2022 | Disposed — authority bench 5 |
Only what the builder declared, or what RERA Karnataka records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with RERA Karnataka, or that this register doesn’t publish it — never that nothing happened.
581 residential projects still under way within 25 km. Step out ring by ring:
Of the 113 projects the radar draws within 6 km — every kind, every stage — 27 are residential projects still under way. This list keeps only those, and looks further out.
5 projects between 1 and 3 km — showing the nearest 5.
SPL PALMS DEVELOPERS PRIVATE LIMITED · Bengaluru North
Vruksha Infra · Bengaluru North
DHARA HOME SPACES · Bengaluru North
Sruthika Builders & Developers · Yelahanka
Karnataka Slum Development Board · Bengaluru North
Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.