Complete project overview

RERA Karnataka · Registration filing
Status
Ongoing
Plots
74 plots
Land parcels
3 survey nos

Timeline

Project startedOct 2025
RERA registeredNov 2025
Proposed completionDec 2028
TodayJul 2026
Construction progress

45% overall, as filed

From the promoter's latest quarterly progress report filed with RERA Karnataka — % complete overall and by stage, as of that filing. A dated snapshot, not a live tracker.

Find your plot

Every plot the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.

UnitTypeTotal sq m
1Plot3921.79
2Plot108
3Plot108
4Plot108
5Plot108
6Plot108
7Plot108
8Plot108
9Plot108
10Plot108
11Plot108
12Plot108
13Plot107.54
14Plot114.03
15Plot129.85
16Plot135
17Plot135
18Plot135
19Plot137.43
20Plot135
21Plot135
22Plot135
23Plot135
24Plot135
25Plot135
26Plot135
27Plot135
28Plot135
29Plot135
30Plot135
31Plot135
32Plot135
33Plot135
34Plot172.48
35Plot404.33
36Plot144
37Plot144
38Plot144
39Plot144
40Plot144
41Plot144
42Plot144
43Plot144
44Plot144
45Plot144
46Plot144
47Plot144
48Plot144
49Plot144
50Plot144
51Plot144
52Plot144
53Plot144
54Plot144
55Plot144
56Plot144
57Plot144
58Plot180
59Plot180
60Plot180
61Plot114.96
62Plot153.03
63Plot177.36
64Plot135.24
65Plot138.35
66Plot142.27
67Plot164.57
68Plot108
69Plot119.12
70Plot171.36
71Plot185.67
72Plot199.40
73Plot203.45
74Plot182.41

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion.

02

Builder’s track record

RERA Karnataka · Promoter registration

Konig Homes

Partnership FirmPromoter type
Bengaluru UrbanBased in
5Projects
2Cities
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
640 plotson the public record across 5 projects
₹219.30 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
BIAPPA - Bangalore Airport Area Planning AuthorityUrban Development Authoritythis project3 of 5 projects
BMRDA - Bangalore Metropolitan Region Development AuthorityUrban Development Authority1 of 5 projects
Local Planning AuthorityTown & Country Planning (DTCP)1 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Devanahalli
District
Bengaluru Rural
Pincode
560067
Address
Sy No. 134/1, 133/3 and 103/1 , Sadahalli Village, Kasaba Hobli , Devanahalli , Bengaluru Rural, Karnataka - 560067
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.9 km · Ballari RoadPrimary road 1.9 km · Airport Trumpet FlyoverRailway line 2.0 kmRailway station 3.0km away (Kempegowda International Airport Halt)Bus stop within 500m
Water & environment
Water body 164 m
distances only — not a flood assessment
Land, title & encumbrance
LandJoint development (JDA) — built on the owner’s land by agreement
ConversionConverted to non-agricultural
LitigationDeclared free of litigation
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹19.10 Cr declared to build 74 plots. What that works out to:

₹25.80 Lakhdeclared cost per plotall-in — land + construction
30%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

BIAPPA - Bangalore Airport Area Planning Authority

Urban Development Authority
approved 10 Sep 2025 · 10 mo ago
Layout Permit no. BIAAPA/TP/LAO/19/2025-2026Survey no. 134/1
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan BIAAPA/TP/LAO/19/2025-2026 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

BIAPPA

Urban Development Authority · Bangalore Airport Area Planning Authority

Has approved 328 RERA projects3.8% of Karnataka.

a plotted-layout market30% apartments · 70% plotted layouts. Your plotted layout is this body's core business.

Builders
236
On record
20,448 flats · 19,692 plots
Reach
8 taluks
Since
2017

More layout-heavy than Karnataka overall — 70% plots here vs 38% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

None on record with RERA Karnataka against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.