HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
27 units
Mix
18 × 3BHK · 9 × 2BHK
Booked
27 of 27 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
1,015 sq m
Floor area
3,946 sq m
Description
SHANOOR NALANDA

Timeline

Project startedJan 2018
RERA registeredMar 2021
Proposed completionJun 2021
TodayJul 2026
Construction progress

88% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 27 available
TypeArea sq mAvailable
2BHK700 of 5
2BHK710 of 4
3BHK1020 of 4
3BHK950 of 4
3BHK960 of 5
3BHK990 of 5

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

SHANOOR PROJECTS AND REALTORS PVT LTD

CompanyPromoter type
Thiruvananthapuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
12Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
486 homes · 66 plotson the public record across 12 projects
63,916 sq mbuilt-up filed
21,963 sq mplotted area
37,897 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Trivandrum Municipal CorporationMunicipal Corporationthis project10 of 12 projects
Kadinamkulam Grama PanchayatGrama Panchayat1 of 12 projects
Trivandrum Muncipal Municipal CorporationMunicipal Corporation1 of 12 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
CHERUVAKKAL
Village
CHERUVAKKAL
Taluk
THIRUVANANTHAPRUAM
District
Thiruvananthapuram
Pincode
695017
Survey no.
311/3
Patta no.
18546
What’s nearby
SchoolsNearest school 1.3km away · College or university 1.1km away · Library 1.0km away
HealthcareHospital 903m away · 1 clinic within 1km
LifestylePark 937m away · Gym or sports centre 1.5km away
ShoppingSupermarket 1.1km away · Mall 1.3km away
Getting around
Expressway 3.0 km · Salem - Kochi - Kanyakumari RoadPrimary road 1.0 kmRailway line 3.6 kmRailway station 3.6km away (Thiruvananthapuram North)Bus stop within 500m
Water & environment
Water body 211 m
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Trivandrum Municipal Corporation

Municipal Corporation
approved 9 May 2014 · 12 yrs ago
Building Permit no. UE1/BA-242/11Survey no. 311/3

The promised possession date (30 Jun 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan UE1/BA-242/11 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Trivandrum Municipal Corporation

Municipal corporation / municipality

Has approved 43 RERA projects2.8% of Kerala.

an apartments market81% apartments · 19% plotted layouts. Apartments like yours are this body's core business.

Builders
24
On record
1,888 flats · 188 plots
Since
2021

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.