Complete project overview

K-RERA · Registration filing
Units
68 units
Mix
35 × 3BHK · 33 × 2BHK
Booked
33 of 68 filed sold/bookedas declared in the RERA filing
Buildings
2
Land area
3,875 sq m
Floor area
12,545 sq m
Description
DD JAL DARSHAN

Timeline

RERA registeredAug 2021
Project startedSep 2021
Proposed completionDec 2026
TodayJul 2026
Construction progress

15% overall, as filed

Sanitary Fittings0%
Electrical Fittings0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
The external plumbing and external plastering3%
Completion of terraces floor each building3%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings8%
Slabs of Super Structure20%
Slabs of Super Structure20%
Staircases, Lifts Wells22%
Basement(s) and Plinth80%
Excavation100%
Excavation100%
Basement(s) and Plinth100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

35 of 68 available
TypeArea sq mAvailable
3BHK1016 of 6
2BHK690 of 3
2BHK602 of 7
3BHK865 of 7
3BHK1015 of 7
2BHK692 of 4
3BHK1012 of 4
3BHK1023 of 4
3BHK1020 of 3
2BHK682 of 4
2BHK681 of 3
2BHK661 of 3
3BHK1013 of 4
2BHK660 of 3
2BHK663 of 3
2BHK650 of 3

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

Desai Rachana Private Limited

CompanyPromoter type
Thiruvananthapuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
5Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
554 homeson the public record across 5 projects
71,343 sq mbuilt-up filed
17,625 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Elamkunnappuzha Grama PanchayatGrama Panchayat1 of 5 projects
Kolazhy Grama PanchayatGrama Panchayat1 of 5 projects
Managalapuram Grama PanchayatGrama Panchayat1 of 5 projects
Thiruvalla MunicipalityMunicipality1 of 5 projects
Thiruvananthpuram Municipal CorporationMunicipal Corporationthis project1 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
Ulloor-Aakkulam Road
Village
CHERUVAKKAL
Taluk
THIRUVANANTHAPRUAM
District
Thiruvananthapuram
Pincode
695017
Survey no.
Re Sy.No 167/10,167/14,167/15,167/7,167/8, Block No.020
Patta no.
25007
What’s nearby
SchoolsNo schools within 2km · Library 1.0km away
HealthcareHospital 927m away · 1 clinic within 1km
LifestylePark 1.3km away · Playground within 500m · 4 restaurants and cafes within 1km
ShoppingSupermarket 1.5km away · Bank 451m away · ATM within 500m
Getting around
Expressway 1.4 kmPrimary road 2.1 kmRailway line 2.0 kmRailway station 1.9km away (Thiruvananthapuram North)Limited bus connectivity nearby
Water & environment
Water body 117 m
distances only — not a flood assessment
04

Planning authority

K-RERA · Approved building plan

Thiruvananthpuram Municipal Corporation

Municipal Corporation
approved 15 Feb 2017 · 9 yrs ago
Building Permit no. UE2/BA/57/15Survey no. Re Sy.No 167/10,167/14,167/15,167/7,167/8, Block No.020
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan UE2/BA/57/15 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Municipal Corporation / Municipality

A city corporation or municipality that sanctions building & development permits within its own limits. It has approved 871 RERA projects across 12 districts about 1 in 2 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.