42 of 53 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
1,620 sq m
Floor area
9,310 sq m
Description
THAKSHASILA
Timeline
Project startedJul 2016
RERA registeredApr 2021
Proposed completionSep 2023
TodaySep 2026
Construction progress
88% overall, as filed
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the builder's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.
Find your flat
Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.
11 of 53 available
TypeArea sq mAvailable
3BHK1030 of 12
2BHK730 of 11
3BHK762 of 9
2BHK652 of 8
3BHK1081 of 1
2BHK694 of 10
1BHK351 of 1
2BHK741 of 1
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the builder declared — not a live booking system.
Complete project overview — done
02
Builder’s track record
K-RERA · Builder registration
RAJTECH DEVELOPERS AND BUILDERS PVT LTD
CompanyPromoter type
Thiruvananthapuram, KeralaBased in
No — the promoter declared this is a first projectDeclared prior experience
The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Schools2 schools within 500m · 4 educational institutions within 1km · College or university 696m away
HealthcareHospital 616m away · Pharmacy within 1km · Doctor's clinic within 1km
LifestylePark 629m away · Gym or sports centre 169m away · 18+ restaurants and cafes within 1km
ShoppingSupermarket 334m away · Mall 800m away · Convenience store within 500m
Getting around
Expressway 3.5 km · Salem - Kochi - Kanyakumari RoadPrimary road 146 mRailway line 3.8 kmRailway station 4.1km away (Kazhakuttam)5 bus stops within 500m
Water & environment
Water body 267 m · Mazhavencherry kulam
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the builder at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Location — done
04
Government Guidance Rate
Kerala Registration Department — fair value
In Kerala it’s called the fair value.
₹3,532per sq yd
₹4,224per sq m
Which rate
Residential Plot with Corp./Mun./Panch. road access
Matched to
The value published for this project's own survey number, in “Pangappara”.
What this number is — and isn’t
The minimum value Kerala’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
Not a market price. Sales normally register above it, and how far above varies by place and by project.
Its fit depends on the grain the state publishes at. This one is matched at the level of parcel, and says so above. How Horizon decides what to show.
Government Guidance Rate — done
05
Planning authority
K-RERA · Approved building plan
Trivandrum Municipal Corporation
Municipal Corporation
approved 2 Aug 2018 · 8 yrs ago
Building Permit no. TP/723/15-16/SZOSurvey no. 344/6,344/20,344/6-1
The promised possession date (30 Sep 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
Verify it yourself — look up plan TP/723/15-16/SZO on the approving authority’s portal to confirm the approval.
The approving body, at scale
Trivandrum Municipal Corporation
Municipal corporation / municipality
Has approved 43 RERA projects — 2.8% of Kerala.
an apartments market — 81% apartments · 19% plotted layouts. Apartments like yours are this body's core business.
Builders
24
On record
1,888 flats · 188 plots
Since
2021
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
Not published. K-RERA doesn’t publish a complaints register in the record Horizon reads.
So there is nothing to count here — which is not the same as nothing having been filed.
What the builder declared
Declared to K-RERA
Litigation
None declared in this filing
Only what the builder declared, or what K-RERA records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with K-RERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
07
Other projects nearby
The register · within 25 km
166 residential projects still under way within 25 km. Step out ring by ring:
Of the 202 projects the radar draws within 6 km — every kind, every stage — 84 are residential projects still under way. This list keeps only those, and looks further out.
2 projects within 1 km — showing the nearest 2.
ULIYAZHATHURAResidential (Apartment)
CONFIDENT HORIZON
Confident Projects Residential
5 yr 2 mo
Aug 2021registered
Oct 2026target completion
Government Guidance Rate₹2,207/sq ydScale100 flatsAuthorityK-RERA
The approving body's other projects: counted by Horizon across the register.
06Complaints & litigation
K-RERA's public record lists no complaints or litigation for this project.
07Other projects nearby
The RERA-registered projects Horizon holds within 25 km of these coordinates.
Compiled by Horizon from public records. Each fact is reproduced as its source publishes it, and Horizon does not verify filings on the ground. The live record: gethorizon.in/projects/thakshasila-pangapara-thiruvananthapuram-t9oguai6.
Horizon does not rate, review, score or signal, and it gives no verdict, opinion or forecast. Its only aim is to seek the truth through data: what the public record says, where each fact comes from, and where the record is silent. Nothing in this document is legal, financial or investment advice; what to make of it is yours to decide.