HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
68 units
Mix
36 × 2BHK · 32 × 3BHK
Booked
68 of 68 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
2,555 sq m
Floor area
11,073 sq m
Description
Oceanus Sunshine Phase II

Timeline

Project startedNov 2014
RERA registeredApr 2021
Proposed completionMar 2022
TodayJul 2026
Construction progress

87% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps etc95%
Fire Fighting Fittings and Equipment95%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc95%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 68 available
TypeArea sq mAvailable
3BHK9470 of 17
2BHK8090 of 13
2BHK8250 of 13
2BHK7800 of 2
2BHK7190 of 4
3BHK9650 of 15
2BHK9260 of 2
2BHK7740 of 2

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

Oceanus Dwellings Pvt Ltd

CompanyPromoter type
Thiruvananthapuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
11Projects
2Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
559 homeson the public record across 11 projects
94,421 sq mbuilt-up filed
43,791 sq mland declared
₹176.89 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thiruvananthapuram Municipal CorporationMunicipal Corporation5 of 11 projects
BBMP - Bruhat Bengaluru Mahanagara PalikeMunicipal / Corporation4 of 11 projects
Kannur MunicipalityMunicipality1 of 11 projects
Thiruvananthapuram Corporation ThiruvananthapuramLocal body (LSGI)this project1 of 11 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
Thrippadhapuram, Kulathoor P. O., Kazhakkuttom, Thiruvananthapuram
Village
ATTIPRA
Taluk
THIRUVANANTHAPRUAM
District
Thiruvananthapuram
Pincode
695583
Survey no.
400/3, 400/4
Patta no.
11335, 12306
What’s nearby
Schools1 school within 500m · 4 educational institutions within 1km · Library 290m away
HealthcareHospital 472m away · 1 clinic within 1km
LifestylePark 1.2km away · Gym or sports centre 805m away · 20+ restaurants and cafes within 1km
ShoppingSupermarket 1.2km away · Bank 118m away · ATM within 500m
Getting around
Expressway 81 m · Salem - Kochi - Kanyakumari RoadPrimary road 2.2 kmRailway line 418 mRailway station 1.4km away (Kazhakuttam)4 bus stops within 500m
Water & environment
Water body 479 mCanal 756 m · Parvathy Puthanar
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Thiruvananthapuram Corporation Thiruvananthapuram

Local body (LSGI)
approved 31 Oct 2013 · 12 yrs ago
Building Permit no. ZAE/BA/216-A/13Survey no. 400/3, 400/4

The promised possession date (30 Mar 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan ZAE/BA/216-A/13 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

The local self-government (LSGI)

The local body that sanctioned this project. It has approved 404 RERA projects across 14 districts about 1 in 4 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.