Timeline

Project startedFeb 2020
RERA registeredJul 2020
Proposed completionOct 2021
TodaySep 2026

Find your flat

Every flat the builder registered. Look yours up and check it is on the record.

UnitType
1Ground Floor3BHK
2Ground Floor2BHK
3Ground Floor1.5BHK
4Ground Floor2BHK
5Ground Floor2BHK
6Ground Floor2BHK
1011st Floor3BHK
1021st Floor2BHK
1031st Floor1.5BHK
1041st Floor3BHK
1051st Floor3BHK
1061st Floor2BHK
2012nd Floor3BHK
2022nd Floor2BHK
2032nd Floor1.5BHK
2042nd Floor3BHK
2052nd Floor3BHK
2062nd Floor2BHK
3013rd Floor3BHK
3023rd Floor2BHK
3033rd Floor1.5BHK
3043rd Floor3BHK
3053rd Floor3BHK
3063rd Floor2BHK
4014th Floor3BHK
4024th Floor2BHK
4034th Floor1.5BHK
4044th Floor3BHK
4054th Floor3BHK
4064th Floor2BHK

Areas are not shown for this project. The sizes filed against these flats are not credible — units recorded as 2 and 3 BHK are filed at sizes no flat is, which usually means square feet were entered in a column the register labels square metres. Publishing those as the registered carpet area would be worse than publishing nothing. The flat numbers and types above are the register’s.

02

Builder’s track record

RERA Karnataka · Builder registration

Bantwal Arundathi R Somayaji

IndividualPromoter type
KarnatakaBased in
1Projects
1City
2020–2021Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Mangalore
District
Dakshina Kannada
Pincode
575003
Address
SOMAYAJI ORCHID, , BEJAI. KODIALBAIL VILLAGE
What’s nearby
Schools3 schools within 1km · 5 educational institutions within 1km · College or university 626m away
HealthcareHospital 511m away · Clinic within 2km · Pharmacy within 1km
LifestyleNo parks within 2km · Gym or sports centre 1.0km away · 3 restaurants and cafes within 1km
ShoppingSupermarket 817m away · Mall 1.4km away · Bank 528m away
Getting around
Expressway 1.0 kmPrimary road 98 m · George Fernandes RoadRailway line 2.4 kmRailway station 2.6km away (Mangaluru Central)Bus stop within 1km
Water & environment
River 121 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹7.42 Cr declared. What that works out to:

20%of the cost is land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Karnataka Department of Stamps & Registration — 2023-24 guidance-value gazettes

In Karnataka it’s called the guidance value.

₹25,084per sq yd
₹30,000per sq m
Which rate
site (guidance value)
Matched to
The rate published for “Orchid ( R) Bendorwell”.
In force
effective Oct 2023

What this number is — and isn’t

  • The minimum value Karnataka’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of locality, and says so above. How Horizon decides what to show.
05

Planning authority

RERA Karnataka · Approved building plan

Mangaluru Urban Development Authority

Urban Development Authority
Building Permit

The promised possession date (30 Oct 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Mangaluru Urban Development Authority

Urban Development Authority

Has approved 440 RERA projectsabout 1 in 20 in Karnataka.

an apartments market96% apartments · 4% plotted layouts. Apartments like yours are this body's core business.

Builders
315
On record
8,036 flats · 698 plots
Reach
6 taluks
Since
2017

More apartment-heavy than Karnataka overall — 96% apartments here vs 62% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by RERA Karnataka

07

Other projects nearby

The register · within 25 km

165 residential projects still under way within 25 km. Step out ring by ring:

Of the 435 projects the radar draws within 6 km — every kind, every stage — 123 are residential projects still under way. This list keeps only those, and looks further out.

19 projects within 1 km — showing the nearest 6.

MangaloreApartment

POORVI ESTELLA

POORVI HOUSING DEVELOPMENT COMPANY PVT. LTD.

Mar 2023started
Feb 2028target completion
Declared cost₹101.46 CrScale136 flatsAuthorityRERA Karnataka
MangaloreMixed Development

ROHAN CITY

ROHAN CORPORATION INDIA PRIVATE LIMITED

Nov 2022started
Nov 2028target completion
Declared cost₹478.73 CrScale852 flatsAuthorityRERA Karnataka
Dakshina KannadaMixed Development

SHREKA PRIDE

SHREKA BUILDERS AND DEVELOPERS

Jun 2025started
Dec 2029target completion
Declared cost₹22.25 CrScale37 flatsAuthorityRERA Karnataka
MangaloreMixed Development

NANDANA

SHREE NIDHI INFRASTRUCTURES

Oct 2023started
Dec 2028target completion
Declared cost₹12.40 CrScale24 flatsAuthorityRERA Karnataka
MangaloreMixed Development

LOTUS PEARL

PRANAVA BUILDERS AND DEVELOPERS

Sep 2025started
Aug 2028target completion
Declared cost₹37.64 CrScale86 flatsAuthorityRERA Karnataka
MangaloreApartment

AGRAJA ATLANTIC

AGRAJA MANJUSHREE

May 2026started
Dec 2033target completion
Declared cost₹46.32 CrScale63 flatsAuthorityRERA Karnataka

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.