01

Complete project overview

K-RERA · Registration filing
Project name
KUDUMBAM
Units
56 units
Mix
52 × 2BHK · 4 × 1BHK
Booked
48 of 56 filed sold/bookedas declared in the RERA filing
Buildings
2
Land area
2,261 sq m
Floor area
4,150 sq m
Description
KUDUMBAM

Timeline

Project startedFeb 2019
RERA registeredJul 2021
Proposed completionDec 2021
TodaySep 2026
Construction progress

88% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the builder's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.

8 of 56 available
TypeArea sq mAvailable
2BHK473 of 19
2BHK471 of 9
2BHK490 of 5
2BHK492 of 4
1BHK360 of 4
2BHK511 of 5
2BHK490 of 5
2BHK471 of 5

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the builder declared — not a live booking system.

02

Builder’s track record

K-RERA · Builder registration

Syama Dynamic Project Developers Private Limited

CompanyPromoter type
Ernakulam, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
1Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
Bhavans Road
Village
NADAMA
Taluk
Kanayannur
District
Ernakulam
Pincode
682306
Survey no.
Block No 186, Re. Sy. No. 51/2, 51/3,52/3,53/2 and 55/3
Patta no.
17979,18567 and 18568
What’s nearby
SchoolsNearest school 1.7km away · Library 1.4km away
HealthcareHospital 999m away · 1 clinic within 1km · Pharmacy within 1km
LifestylePark 1.2km away · Gym or sports centre 1.1km away
ShoppingSupermarket 779m away · Mall 901m away · Convenience store within 1km
Getting around
Expressway 1.4 kmPrimary road 780 mRailway line 1.3 kmMetro station 864m away (Thykoodam)Bus stop within 1km
Water & environment
Water body 253 mCanal 1.2 km
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the builder at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Government Guidance Rate

Kerala Registration Department — fair value

In Kerala it’s called the fair value.

₹5,518per sq yd
₹6,600per sq m
Which rate
Residential Plot without vehicular access
Matched to
The value published for this project's own survey number, in “Nadama”.

What this number is — and isn’t

  • The minimum value Kerala’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of parcel, and says so above. How Horizon decides what to show.
05

Planning authority

K-RERA · Approved building plan

Tripunithura

Local body (LSGI)
approved 16 May 2018 · 8 yrs ago
Building Permit no. PW2/BA88/18-19Survey no. Block No 186, Re. Sy. No. 51/2, 51/3,52/3,53/2 and 55/3

The promised possession date (30 Dec 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

Verify it yourself — look up plan PW2/BA88/18-19 on the approving authority’s portal to confirm the approval.

The approving body, at scale

The local self-government (LSGI)

The local body that approved this project. It has approved 404 RERA projects across 14 districts about 1 in 4 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

187 residential projects still under way within 25 km. Step out ring by ring:

Of the 229 projects the radar draws within 6 km — every kind, every stage — 91 are residential projects still under way. This list keeps only those, and looks further out.

2 projects within 1 km — showing the nearest 2.

NADAMAResidential (Apartment)

Sobha Atlantis Phase 2 block 1 and 2

Sobha Limited

Feb 2024registered
Dec 2029target completion
Government Guidance Rate₹11,037/sq ydScale192 flatsAuthorityK-RERA
NADAMAResidential (Apartment)

Sobha Atlantis Phase 1 block 3 and 4

Sobha Limited

Sep 2021registered
Jun 2026target completion
Government Guidance Rate₹8,278/sq ydScale192 flatsAuthorityK-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.