HORIZON
Share

PAVILION

RAJ/P/2023/2395 · RAJ-RERA · https://gethorizon.in/projects/pavilion-jaipur-tyasvb3j

01

Complete project overview

RAJ-RERA · Registration filing
Project name
PAVILION
Units
13 units
Mix
6 × OFFICE TYPE-1 · 6 × OFFICE TYPE-2 · 1 × SHOWROOM
Carpet area
145–245 sq mper-type range, as filed
Land area
1,115 sq m
Description
Plot Area= 1114.80 sq mtrs less surrendered area= 92.90sq.mtrs. Hence, Net plot area =1021.90 sq mtrs (i.e. 1114.80-92.90). Thus, net plot area of 1021.90 sq. mtrs is mentioned in phase area of the project.

Timeline

Construction startJan 2023
RERA registeredFeb 2023
Proposed completionMar 2025
TodaySep 2026

Find your unit

Filed by type and size, in the batches the builder registered — not a per-unit listing. Look yours up.

13 units across 3 batches
BuildingTypeArea sq mCount
PAVILIONOFFICE TYPE-12266
PAVILIONOFFICE TYPE-21456
PAVILIONSHOWROOM2451

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Builder registration

SUKHANI BUILDERS AND DEVELOPERS

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2023–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
PLOT NO. SB-56, BAPU NAGAR, TONK ROAD, JAIPUR, Jaipur, Jaipur, 302015
Village
JAIPUR
Taluka
Jaipur
District
Jaipur
Pincode
302015
What’s nearby
Schools1 school within 500m · 7 educational institutions within 1km · College or university 399m away
HealthcareHospital 153m away · 6 clinics within 1km · Doctor's clinic within 1km
Lifestyle1 park within 500m · 5 restaurants and cafes within 1km
ShoppingSupermarket 1.5km away · Mall 1.8km away · Bank 500m away
Getting around
Expressway 2.7 km · Mirza Ismail RoadPrimary road 240 m · Sawai Mansingh RoadRailway line 1.5 kmRailway station 2.2km away (Bais Godam)6 bus stops within 500m
Water & environment
Water body 1.0 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹32.00 Cr declared to build 13 flats. What that works out to:

₹2.46 Crdeclared cost per flatall-in — land + construction
₹6,077/sq ftof built-up area₹65,411/sq m
53%of the cost is land₹14,167/sq ft of land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Rajasthan registration department

In Rajasthan it’s called the DLC rate.

No government guidance rate is shown for this project.

Rajasthan's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 20 Feb 2023 · 3 yrs ago

The promised possession date (31 Mar 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

07

Other projects nearby

The register · within 25 km

15 commercial projects still under way within 25 km. Step out ring by ring:

Of the 206 projects the radar draws within 6 km — every kind, every stage — 4 are commercial projects still under way. This list keeps only those, and looks further out.

2 projects within 3 km — showing the nearest 2.

2.4 km awayCommercial

GT Bellevue

R AND R CONSORTIUM PVT. LTD. · Jaipur

Jan 2025registered
Dec 2026target completion
Declared cost₹29.64 CrScale24 flatsAuthorityRAJ-RERA
2.4 km awayCommercial

JEWEL TOWER

Suncity Projects Private Limited · Jaipur

Dec 2023registered
Dec 2026target completion
Declared cost₹131.00 CrScale145 flatsAuthorityRAJ-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.