3 extensions on record — latest to 17 May 2022declared reason: force majeure
Description
1. We have uploaded site plan along with sale deed & copy of legal title report under head - Project related legal document.
As per applicant request application,to change in Bank account and further to the approval of Hon'able Chairman on 20/12/2019,Bank account changed from Axis Bank,Malviya nagar Branch,New Delhi to Canara Bank,Arvind marg main(362),Jaipur.Bank account details changed on 07/01/2020.
2. As per applicant request application to change in estimated finish date and further to the approval of Hon'ble Chairman, the estimated finish date has been changed from 18.05.2019 to 17.05.2020. Therefore the revised estimated finish date should be read as 17.05.2020
3. Revised maps of approval dated 25-05-2018 from JDA uploaded under the Structural drawings tab of Building Documents column on 07-08-2020. This bears the approval of Honorable Chairman sir.
The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Schools1 school within 1km · 5 educational institutions within 1km · College or university 717m away
HealthcareHospital 147m away · 3 clinics within 1km · Doctor's clinic within 1km
LifestylePark 986m away · 32+ restaurants and cafes within 1km · Swimming pool within 2km
ShoppingSupermarket 967m away · Mall 976m away · Convenience store within 1km
Getting around
Expressway 912 m · Sardar Patel RoadPrimary road 1.0 km · Mirza Ismail RoadRailway line 1.2 kmRailway station 1.5km away (Bais Godam)Bus stop within 500m
Water & environment
Canal 85 mWater body 652 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price
₹530.30 Cr declared. What that works out to:
30%of the cost is land
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Location & price analysis — done
04
Government Guidance Rate
Rajasthan registration department
In Rajasthan it’s called the DLC rate.
No government guidance rate is shown for this project.
Rajasthan's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
05
Planning authority
RAJ-RERA · Approved building plan
Jaipur Development Authority
Development Authority
Building Permitapproved 31 Oct 2017 · 8 yrs ago
The promised possession date (17 May 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
The approving body, at scale
Jaipur Development Authority
Development authority
Has approved 644 RERA projects — about 1 in 3 in Rajasthan, more than any other body in the state.
a mixed market — 52% apartments · 48% plotted layouts.
Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017
More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
Not published. RAJ-RERA doesn’t publish a complaints register in the record Horizon reads.
So there is nothing to count here — which is not the same as nothing having been filed.
What the builder declared
Declared to RAJ-RERA
Litigation
None declared in this filing
Only what the builder declared, or what RAJ-RERA records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with RAJ-RERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
07
Other projects nearby
The register · within 25 km
419 residential projects still under way within 25 km. Step out ring by ring:
Of the 210 projects the radar draws within 6 km — every kind, every stage — 76 are residential projects still under way. This list keeps only those, and looks further out.