Presently as on date we have received building permission from Nagar Nigam Greater Jaipur vide letter dated 03.07.2024 for construction as basement + stilt+ 9th floor, also we have received NOC from Airport Authority with regard to height as upto 32.38 mtrs. (Basement+stilt+9th floor), however Promoter intends to pursue the approval for 10th floor (height) according from Airport Authority which is subject to approval in future from Airport Authority and if we receive NOC for construction of 10th floor from Airport Authority, we shall get 10th floor map released from Nagar Nigam Greater Jaipur subject to approval if allowed. This fact is made to ensure the transparency with the prospective allottees.
There are 18 apartments and 15 stores in the project. We have not associated/linked the stores with apartment and accordingly mentioned the stores details separately under the tab named as ‘Building Details’ due to which there were a discrepancy in the total number of units mentioned in the tab named as ‘Land details of registering project’ and ‘Building Details’. To remove the same, we have mentioned the total number of units as 33. It is to clarify that there are 18 apartments and 15 stores in the project. Further, it is to mention that we will sell the stores along with the units only, to the allottees of the project only. We will not sell the stores separately. We have not yet decided that which store will be sold with which unit number. The said stores will be sold as per the requirement and demand of the allottees.
Timeline
Construction startJan 2025
RERA registeredApr 2025
Proposed completionMar 2028
TodaySep 2026
Find your flat
Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).
The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Schools1 school within 1km · 4 educational institutions within 1km · College or university 902m away
HealthcareHospital 92m away · 17 clinics within 1km · Doctor's clinic within 1km
LifestylePark 547m away · 3 restaurants and cafes within 1km
ShoppingSupermarket 1.9km away · Bank 981m away
Getting around
Expressway 2.3 km · Mirza Ismail RoadPrimary road 483 m · JLN MargRailway line 2.6 kmRailway station 3.1km away (Bais Godam)Bus stop within 1km
Water & environment
Water body 1.4 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price
₹35.72 Cr declared to build 33 flats. What that works out to:
₹1.08 Crdeclared cost per flatall-in — land + construction
₹5,318/sq ftof built-up area₹57,242/sq m
59%of the cost is land₹14,865/sq ft of land
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Location & price analysis — done
04
Government Guidance Rate
Rajasthan registration department
In Rajasthan it’s called the DLC rate.
No government guidance rate is shown for this project.
Rajasthan's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
05
Planning authority
RAJ-RERA · Approved building plan
Jaipur Development Authority
Development Authority
Building Permitapproved 8 Apr 2025 · 1 yr ago
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
The approving body, at scale
Jaipur Development Authority
Development authority
Has approved 644 RERA projects — about 1 in 3 in Rajasthan, more than any other body in the state.
a mixed market — 52% apartments · 48% plotted layouts.
Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017
More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
Not published. RAJ-RERA doesn’t publish a complaints register in the record Horizon reads.
So there is nothing to count here — which is not the same as nothing having been filed.
What the builder declared
Declared to RAJ-RERA
Litigation
None declared in this filing
Only what the builder declared, or what RAJ-RERA records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with RAJ-RERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
07
Other projects nearby
The register · within 25 km
417 residential projects still under way within 25 km. Step out ring by ring:
Of the 173 projects the radar draws within 6 km — every kind, every stage — 57 are residential projects still under way. This list keeps only those, and looks further out.