01

Complete project overview

RAJ-RERA · Registration filing
Land area
1,270 sq m

Timeline

Construction startApr 2013
RERA registeredOct 2017
Proposed completionSep 2018
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

Reyansh Infrastructure Private Limited

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2017–2018Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
17,37,38, Sahkar Marg, Lal Kothi, Bhojpura, Jaipur, Jaipur, 302015
Village
Bhojpura
Taluka
Jaipur
District
Jaipur
Pincode
302015
What’s nearby
SchoolsNearest school 1.1km away · College or university 1.7km away
HealthcareHospital 458m away · 9 clinics within 1km
LifestylePark 1.3km away · 4 restaurants and cafes within 1km
ShoppingSupermarket 869m away · Mall 2.0km away · Convenience store within 1km
Getting around
Expressway 2.0 kmPrimary road 1.2 kmRailway line 71 mRailway station 934m away (Bais Godam)Bus stop within 1km
Water & environment
Canal 145 m · Kartar Pura Nala
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹26.00 Cr declared. What that works out to:

65%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Jaipur Development Authority

Development Authority
Building Permitapproved 17 Oct 2017 · 8 yrs ago

The promised possession date (30 Sep 2018) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Jaipur Development Authority

Development authority

Has approved 644 RERA projectsabout 1 in 3 in Rajasthan, more than any other body in the state.

a mixed market52% apartments · 48% plotted layouts.

Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017

More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.