Note 1) Under Common Details tab, parking is marked as per the approved drawing and calculation table and a stated logic that, all the vehicles that are fully covered (within outer most projection line on both sides) are marked as parked on stilt floor and any uncovered or semi-covered vehicle is marked as parked in open area including handicap parking. The visitors parking is provided over and above the parking provided and hence marked under open area. 2) The open area is mentioned as per the certificate issued by the architect which is attached under Documents Tab. 3) The promoter has provisioned the common amenity, gym and indoor game room at basement floor of the building and common terrace and common swimming pool at the terrace of the building, which being a facility is for the use of the residents of the building and not for sale. 4) The promoter has also provisioned for two private terrace which shall be available with unit 601 and 602 of the 6th floor which is duly marked under Apartment Wise Detail Tab. Kindly take a note.
Timeline
Construction startJan 2025
RERA registeredJul 2025
Proposed completionJan 2027
TodaySep 2026
Find your flat
Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.
12 units across 4 batches
BuildingTypeArea sq mCount
THE ANTILLIAFloor:Unit No.: 1st:101, 2nd:201, 3rd:301, 4th:401, 5th:501 = All 4BHK2105
THE ANTILLIAFloor:Unit No.: 1st:102, 2nd:202, 3rd:302, 4th:402, 5th:502 = All 4BHK2195
THE ANTILLIAFloor:Unit No.: 6th : 601 = 4BHK2101
THE ANTILLIAFloor:Unit No.: 6th : 602 = 4BHK2191
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).
Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Expressway 537 m · Mirza Ismail RoadPrimary road 819 m · Mirza Ismail RoadRailway line 1.6 kmMetro station 1.3km away (Sindhi Camp)3 bus stops within 500m
Water & environment
Canal 207 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price
₹16.48 Cr declared to build 12 flats. What that works out to:
₹1.37 Crdeclared cost per flatall-in — land + construction
₹3,435/sq ftof built-up area₹36,972/sq m
36%of the cost is land₹6,238/sq ft of land
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Location & price analysis — done
04
Government Guidance Rate
Rajasthan registration department
In Rajasthan it’s called the DLC rate.
No government guidance rate is shown for this project.
Rajasthan's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
05
Planning authority
RAJ-RERA · Approved building plan
Building Permitapproved 17 Jul 2025 · 1 yr ago
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
Planning authority — done
06
Complaints & litigation
RAJ-RERA · public record
Complaints register
Not published. RAJ-RERA doesn’t publish a complaints register in the record Horizon reads.
So there is nothing to count here — which is not the same as nothing having been filed.
What the builder declared
Declared to RAJ-RERA
Litigation
None declared in this filing
Only what the builder declared, or what RAJ-RERA records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with RAJ-RERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
07
Other projects nearby
The register · within 25 km
417 residential projects still under way within 25 km. Step out ring by ring:
Of the 181 projects the radar draws within 6 km — every kind, every stage — 65 are residential projects still under way. This list keeps only those, and looks further out.
7 projects within 1 km — showing the nearest 6.
340 m awayGroup Housing
Trimurty Divinity
TRIMURTY COLONIZERS AND BUILDERS PRIVATE LIMITED · Jaipur