Complete project overview

RAJ-RERA · Registration filing
Land area
3,220 sq m

Timeline

Construction startFeb 2013
RERA registeredAug 2017
Proposed completionJun 2019
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

FINETECH PARKCON INDIA PRIVATE LIMITED

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2017–2019Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
ASHOK MARG NALA (Ashok Marg to Malviya Marg) , Ashok Marg, C-Scheme, Jaipur, Jaipur, 302001
Taluka
Jaipur
District
Jaipur
Pincode
302001
What’s nearby
Schools1 school within 500m · 8 educational institutions within 1km · College or university 457m away
HealthcareHospital 260m away · 4 clinics within 1km · Pharmacy within 1km
LifestylePark 721m away · 52+ restaurants and cafes within 1km · Swimming pool within 2km
ShoppingSupermarket 710m away · Mall 642m away · Bank 525m away
Getting around
Expressway 601 m · Mirza Ismail RoadPrimary road 752 m · Mirza Ismail RoadRailway line 1.4 kmMetro station 1.3km away (Sindhi Camp)2 bus stops within 500m
Water & environment
Canal 47 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹39.20 Cr declared. What that works out to:

3%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 30 Aug 2017 · 8 yrs ago

The promised possession date (30 Jun 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.