Complete project overview

RAJ-RERA · Registration filing
Units
8 units
Mix
8 × 3 BHK
Carpet area
156 sq mper-type range, as filed
Land area
711 sq m
Completion deadline extended
2 extensions on record — latest to 10 Mar 2023declared reason: other than force majeure
Description
Due to mistake land and development cost was wrongly filled. Therefore, in place of values filled under Project Cost Detail table the following values should be considered: 1. Land cost as per rule 5(1)= 2,83,44,000.00/- 2. Development cost as per rule 5(2)= 5,00,00,000.00/- 3. TOTAL COST OF THE PROJECT=7,83,44,000.00/-.As per remark the correct phase area has been rectified in Land Details of Registering Project.

Timeline

RERA registeredDec 2017
Proposed completionNov 2019
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

8 units across 1 batch
BuildingTypeArea sq mCount
Wisteria3 BHK1568

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

ELEMENTS INFRADEVELOPMENT PRIVATE LIMITED

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2017–2019Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
C 145, Tilak Nagar, Jaipur, Jaipur, 302004
Taluka
Jaipur
District
Jaipur
Pincode
302004
What’s nearby
SchoolsNearest school 1.6km away · College or university 649m away · Library 1.9km away
HealthcareHospital 351m away · 9 clinics within 1km · Doctor's clinic within 1km
Lifestyle1 park within 500m
ShoppingSupermarket 1.9km away
Getting around
Expressway 2.2 kmPrimary road 1.3 km · JLN MargRailway line 3.1 kmRailway station 3.3km away (Gandhi Nagar Jaipur)Bus stop within 1km
Water & environment
Water body 588 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹6.70 Cr declared to build 8 flats. What that works out to:

₹83.75 Lakhdeclared cost per flatall-in — land + construction
₹2,748/sq ftof built-up area₹29,582/sq m
33%of the cost is land₹2,873/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Jaipur Development Authority

Development Authority
Building Permitapproved 14 Dec 2017 · 8 yrs ago

The promised possession date (19 Nov 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Jaipur Development Authority

Development authority

Has approved 644 RERA projectsabout 1 in 3 in Rajasthan, more than any other body in the state.

a mixed market52% apartments · 48% plotted layouts.

Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017

More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.