2 extensions on record — latest to 25 Apr 2026declared reason: other than force majeure
Description
1. We have taken 10% visitor parking out of total parking approved
Timeline
Construction startFeb 2023
RERA registeredNov 2023
Proposed completionApr 2024
TodaySep 2026
Find your unit
Filed by type and size, in the batches the builder registered — not a per-unit listing. Look yours up.
14 units across 14 batches
BuildingTypeArea sq mCount
Atulyam7011751
Atulyam1021761
Atulyam2011751
Atulyam1011751
Atulyam3011751
Atulyam5011751
Atulyam6021761
Atulyam4011751
Atulyam4021761
Atulyam6011751
Atulyam2021761
Atulyam7021761
Atulyam5021761
Atulyam3021761
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).
The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Schools1 school within 1km · 8 educational institutions within 1km · College or university 404m away
HealthcareHospital 186m away · 9 clinics within 1km · Doctor's clinic within 1km
LifestylePark 553m away
ShoppingNo supermarket within 2km · ATM within 500m
Getting around
Expressway 2.7 kmPrimary road 441 m · JLN MargRailway line 2.4 kmRailway station 2.7km away (Gandhi Nagar Jaipur)Bus stop within 500m
Water & environment
Water body 1.1 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price
₹5.75 Cr declared to build 14 flats. What that works out to:
₹41.07 Lakhdeclared cost per flatall-in — land + construction
₹1,401/sq ftof built-up area₹15,077/sq m
1%of the cost is land₹38/sq ft of land
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Location & price analysis — done
04
Government Guidance Rate
Rajasthan registration department
In Rajasthan it’s called the DLC rate.
No government guidance rate is shown for this project.
Rajasthan's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
05
Planning authority
RAJ-RERA · Approved building plan
Building Permitapproved 5 Nov 2023 · 2 yrs ago
The promised possession date (25 Apr 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
Planning authority — done
06
Complaints & litigation
RAJ-RERA · public record
Complaints register
Not published. RAJ-RERA doesn’t publish a complaints register in the record Horizon reads.
So there is nothing to count here — which is not the same as nothing having been filed.
What the builder declared
Declared to RAJ-RERA
Litigation
None declared in this filing
Only what the builder declared, or what RAJ-RERA records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with RAJ-RERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
07
Other projects nearby
The register · within 25 km
417 residential projects still under way within 25 km. Step out ring by ring:
Of the 195 projects the radar draws within 6 km — every kind, every stage — 60 are residential projects still under way. This list keeps only those, and looks further out.