HORIZON
Share

Trimurty Divinity

RAJ/P/2021/1622 · RAJ-RERA · https://gethorizon.in/projects/trimurty-divinity-jaipur-a7odzecm

01

Complete project overview

RAJ-RERA · Registration filing
Units
59 units
Mix
10 × F-04-Floor 1-8,10&11 · 10 × F-02-Floor 1-8,10&11 · 10 × F-05-Floor-1-8,10&11 · 10 × F-03-Floor 1-8,10&11 · 9 × F-01 -Floor 1-8,10&11 · 1 × F-04 Floor 12
Carpet area
126–179 sq mper-type range, as filed
Land area
2,516 sq m
Completion deadline extended
1 extension on record — latest to 31 Mar 2026declared reason: other than force majeure
Description
Jaipur Municipal Corporation (Heritage) vide their approval letter dated 02.02.2021 has granted permission for construction up to 32 meters height (Lower Basement + Upper basement + Stilt + 9Floors). We will be constructing the project upto Lower Basement + Upper basement + Stilt + 12 Floors, the approval of the same is pending from Competent Authority. However, all the details such as Gross built-up area, apartment type details, development cost has been mentioned considering the project upto Lower Basement + Upper basement + Stilt + 12 Floors. We will update the map on portal as soon as we will get these maps approved from Competent Authority.

Timeline

RERA registeredAug 2021
Construction startAug 2021
Proposed completionMar 2025
TodaySep 2026

Find your unit

Filed by type and size, in the batches the builder registered — not a per-unit listing. Look yours up.

59 units across 15 batches
BuildingTypeArea sq mCount
Trimurty DivinityF-04-Floor 1-8,10&1112610
Trimurty DivinityF-01 -Floor 1-8,10&111379
Trimurty DivinityF-02-Floor 1-8,10&1113310
Trimurty DivinityF-04 Floor 121261
Trimurty DivinityF-05-Floor-1-8,10&1117910
Trimurty DivinityF-03-Floor 1-8,10&1113010
Trimurty DivinityF-02 Floor 91331
Trimurty DivinityF-05 Floor 91791
Trimurty DivinityF-01 Floor 121371
Trimurty DivinityF-02 Floor 121331
Trimurty DivinityF-03 Floor 121301
Trimurty DivinityF-05 Floor 121791
Trimurty DivinityF-01 Floor 91271
Trimurty DivinityF-03 Floor 91301
Trimurty DivinityF-04 Floor 91261

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Builder registration

TRIMURTY COLONIZERS AND BUILDERS PRIVATE LIMITED

OrganisationPromoter type
Jaipur, RajasthanBased in
2Projects
1City
2017–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
59 homeson the public record across 2 projects
18,186 sq mbuilt-up filed
4,402 sq mland declared
₹75.43 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from TRIMURTY COLONIZERS AND BUILDERS PRIVATE LIMITED— the full portfolio →

03

Location & price analysis

RAJ-RERA · Registration filing
Address
C-33, MALVIYA MARG C-SCHEME, Jaipur, Jaipur, 302001
Village
MALVIYA MARG C-SCHEME
Taluka
Jaipur
District
Jaipur
Pincode
302001
What’s nearby
Schools2 schools within 1km · 8 educational institutions within 1km · College or university 557m away
HealthcareHospital 65m away · 4 clinics within 1km · Pharmacy within 1km
LifestylePark 782m away · 52+ restaurants and cafes within 1km · Swimming pool within 2km
ShoppingSupermarket 476m away · Mall 607m away · Bank 521m away
Getting around
Expressway 408 m · Mirza Ismail RoadPrimary road 514 m · Mirza Ismail RoadRailway line 1.3 kmMetro station 1.1km away (Sindhi Camp)4 bus stops within 500m
Water & environment
Canal 279 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹61.01 Cr declared to build 59 flats. What that works out to:

₹1.03 Crdeclared cost per flatall-in — land + construction
₹3,802/sq ftof built-up area₹40,926/sq m
63%of the cost is land₹14,219/sq ft of land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Rajasthan IGRS — DLC rates

In Rajasthan it’s called the DLC rate.

₹43,897per sq yd
₹52,500per sq m
Which rate
residential, interior plot
Matched to
The rate published for the village of “C - Scheme”.
Highest rate
₹71,907 per sq yd — the top road-facing rate among the 48 residential rates published for this village

By the road it faces

interior plot₹52,500 / sq m₹43,897 / sq yd
road-facing₹61,000 / sq m₹51,004 / sq yd
41–60 ft road₹67,100 / sq m₹56,104 / sq yd
61–99 ft road₹77,630 / sq m₹64,909 / sq yd

The same land, priced by the width of the road it faces — each band the middle of the residential rates published for this village.

What this number is — and isn’t

  • The minimum value Rajasthan’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 20 Aug 2021 · 5 yrs ago

The promised possession date (31 Mar 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

07

Other projects nearby

The register · within 25 km

417 residential projects still under way within 25 km. Step out ring by ring:

Of the 198 projects the radar draws within 6 km — every kind, every stage — 70 are residential projects still under way. This list keeps only those, and looks further out.

9 projects within 1 km — showing the nearest 6.

JaipurGroup Housing

The Residence

K. G. KOTHARI PRIMEHOMES LLP

Jun 2023registered
Nov 2027target completion
Declared cost₹76.00 CrScale33 flatsAuthorityRAJ-RERA
JaipurGroup Housing

Kanchan Tara

RIDHI SIDHI PRIME REALTY LLP

Apr 2025registered
Aug 2027target completion
Declared cost₹29.53 CrScale27 flatsAuthorityRAJ-RERA
JaipurGroup Housing

THE ANTILLIA

SHRI GANESH ENTERPRISES

Jul 2025registered
Jan 2027target completion
Declared cost₹16.48 CrScale12 flatsAuthorityRAJ-RERA
JaipurGroup Housing

HANUMAN NILAYAM

SIDDHARTH ASSOCIATES

Jan 2024registered
Sep 2026target completion
Declared cost₹13.90 CrScale31 flatsAuthorityRAJ-RERA
JaipurGroup Housing

STAR PINNACLE

M/s Bardawat Builders And Contractors

Jan 2022registered
May 2026target completion
possession revisedDeclared cost₹15.00 CrScale40 flatsAuthorityRAJ-RERA
JaipurGroup Housing

Okay Plus Ruby Suites

RUBY SUITES LLP

Oct 2023registered
Dec 2026target completion
Declared cost₹18.78 CrScale112 flatsAuthorityRAJ-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.