PADAM PRIME

RAJ/P/2017/287 · RAJ-RERA · https://gethorizon.in/projects/padam-prime-jaipur-4d6823bv

01

Complete project overview

RAJ-RERA · Registration filing
Project name
PADAM PRIME
Land area
1,284 sq m
Completion deadline extended
1 extension on record — latest to 30 Jun 2019
Description
As per Applicant request application w.r.t. Extension of Estimated Finished date and further to the approval of Hon'ble Chairman on 06-02-2020, the estimated finished date has been changed from 01-07-2018 to 30-06-2019.Therefore revised estimated finished date should be now read as 30-06-2019. Estimated finished date updated on 17-02-2020.

Timeline

Construction startJul 2014
RERA registeredOct 2017
Proposed completionJun 2019
TodaySep 2026
02

Builder’s track record

RAJ-RERA · Builder registration

JAIPUR INVESTMENT LIMITED

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2017–2019Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
S-5, KABIR MARG, BANIPARK, JAIPUR, Jaipur, Jaipur, 302016
Taluka
Jaipur
District
Jaipur
Pincode
302016
What’s nearby
Schools1 school within 500m · 5 educational institutions within 1km
HealthcareHospital 129m away · 5 clinics within 1km · Pharmacy within 500m
LifestylePark 1.1km away · 56+ restaurants and cafes within 1km
ShoppingSupermarket 466m away · Mall 988m away · Convenience store within 500m
Getting around
Expressway 1.2 km · Church roadPrimary road 232 m · Sawai Jai Singh CircleRailway line 574 mRailway station 585m away (Jaipur Junction)2 bus stops within 500m
Water & environment
Water body 809 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹14.00 Cr declared. What that works out to:

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Rajasthan registration department

In Rajasthan it’s called the DLC rate.

No government guidance rate is shown for this project.

Rajasthan's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

RAJ-RERA · Approved building plan

Jaipur Development Authority

Development Authority
Building Permitapproved 5 Oct 2017 · 8 yrs ago

The promised possession date (30 Jun 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Jaipur Development Authority

Development authority

Has approved 644 RERA projectsabout 1 in 3 in Rajasthan, more than any other body in the state.

a mixed market52% apartments · 48% plotted layouts.

Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017

More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by RAJ-RERA

07

Other projects nearby

The register · within 25 km

419 residential projects still under way within 25 km. Step out ring by ring:

Of the 243 projects the radar draws within 6 km — every kind, every stage — 90 are residential projects still under way. This list keeps only those, and looks further out.

10 projects within 1 km — showing the nearest 6.

250 m awayGroup Housing

Gurukripa Aaradhya

M/s New Leaf Developers · Jaipur

Jul 2026registered
Sep 2028target completion
Declared cost₹33.50 CrScale80 flatsAuthorityRAJ-RERA
540 m awayGroup Housing

EVAARAH

RESONANCE BUILDERS · Jaipur

Jan 2026registered
Jan 2031target completion
Declared cost₹113.73 CrScale66 flatsAuthorityRAJ-RERA
620 m awayGroup Housing

Om Shivanta

Om Builders and Developers · Jaipur

Oct 2024registered
Apr 2028target completion
Declared cost₹10.46 CrScale18 flatsAuthorityRAJ-RERA
680 m awayGroup Housing

KEDIA'S TULSI

KEDIA ELITE BUILDERS PRIVATE LIMITED · Jaipur

Jul 2024registered
Dec 2026target completion
Declared cost₹48.02 CrScale24 flatsAuthorityRAJ-RERA
750 m awayGroup Housing

SHIVA

STAR DEVELOPERS · Jaipur

Jul 2024registered
May 2028target completion
Declared cost₹84.00 CrScale71 flatsAuthorityRAJ-RERA
770 m awayGroup Housing

Unique Prestige

ROYAL INFRA PROJECTS · Jaipur

May 2024registered
Dec 2027target completion
Declared cost₹6.71 CrScale18 flatsAuthorityRAJ-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.