Upasana First Avenue

RAJ/P/2017/534 · RAJ-RERA · https://gethorizon.in/projects/upasana-first-avenue-jaipur-jkl6xw9v

01

Complete project overview

RAJ-RERA · Registration filing
Land area
1,483 sq m
Completion deadline extended
1 extension on record — latest to 31 Dec 2022declared reason: force majeure

Timeline

RERA registeredDec 2017
Construction startJan 2018
Proposed completionDec 2021
TodaySep 2026
02

Builder’s track record

RAJ-RERA · Builder registration

Upasana Colonisers and Resorts Private Limited

OrganisationPromoter type
Jaipur, RajasthanBased in
3Projects
1City
2017–2021Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
3 projectson the public record across 3 projects
23,602 sq mbuilt-up filed
5,015 sq mland declared
₹57.66 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from Upasana Colonisers and Resorts Private Limited— the full portfolio →

03

Location & price analysis

RAJ-RERA · Registration filing
Address
B-92, In Gopal Badi scheme, Ajmer Road, Jaipur, Jaipur, 302001
Taluka
Jaipur
District
Jaipur
Pincode
302001
What’s nearby
Schools2 schools within 1km · 3 educational institutions within 1km · College or university 1.6km away
HealthcareHospital 221m away · 5 clinics within 1km · Pharmacy within 500m
Lifestyle1 park within 500m · 70+ restaurants and cafes within 1km · Swimming pool within 2km
ShoppingSupermarket 506m away · Mall 1.6km away · Bank 565m away
Getting around
Expressway 245 m · Ajmer RoadPrimary road 416 m · Mirza Ismail RoadRailway line 235 mMetro station 339m away (Railway Station)10 bus stops within 500m
Water & environment
Canal 1.2 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹32.00 Cr declared. What that works out to:

66%of the cost is land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Rajasthan registration department

In Rajasthan it’s called the DLC rate.

No government guidance rate is shown for this project.

Rajasthan's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 12 Dec 2017 · 8 yrs ago

The promised possession date (31 Dec 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

07

Other projects nearby

The register · within 25 km

419 residential projects still under way within 25 km. Step out ring by ring:

Of the 227 projects the radar draws within 6 km — every kind, every stage — 84 are residential projects still under way. This list keeps only those, and looks further out.

8 projects within 1 km — showing the nearest 6.

360 m awayGroup Housing

FORTUNE PALACE B

SHRI VINAYAK BUILDERS · Sanganer · Jaipur

May 2025registered
Mar 2026target completion
Declared cost₹14.00 CrScale36 flatsAuthorityRAJ-RERA
550 m awayGroup Housing

Okay Plus Ruby Suites

RUBY SUITES LLP · Jaipur

Oct 2023registered
Dec 2026target completion
Declared cost₹18.78 CrScale112 flatsAuthorityRAJ-RERA
600 m awayGroup Housing

Sawai

AKSHAT APARTMENTS PRIVATE LIMITED · Jaipur

Mar 2024registered
Dec 2028target completion
Declared cost₹722.00 CrScale96 flatsAuthorityRAJ-RERA
680 m awayGroup Housing

FORTUNE PALACE D

SIDDHI VINAYAK BUILDERS · Sanganer · Jaipur

Apr 2025registered
Mar 2026target completion
Declared cost₹15.00 CrScale42 flatsAuthorityRAJ-RERA
780 m awayGroup Housing

Gurukripa Aaradhya

M/s New Leaf Developers · Jaipur

Jul 2026registered
Sep 2028target completion
Declared cost₹33.50 CrScale80 flatsAuthorityRAJ-RERA
860 m awayGroup Housing

AAROHAN

URBAN VIEW DEVELOPERS LLP · Jaipur

Nov 2023registered
Apr 2028target completion
Declared cost₹235.27 CrScale64 flatsAuthorityRAJ-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.