Complete project overview

UP-RERA · Registration filing
Units
480 units
Unit mix
480 × 1 BHK
Carpet area
23 sq mper unit, as filed
Floors
3
Blocks
10
Land area
15,410 sq m

Timeline

Project startedAug 2020
RERA registeredJan 2023
Proposed completionDec 2024
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

480 units across 40 batches
BuildingFloorTypeArea sq mCount
Tower 1GF1 BHK2312
Tower 111 BHK2312
Tower 121 BHK2312
Tower 131 BHK2312
Tower 10GF1 BHK2312
Tower 1011 BHK2312
Tower 1021 BHK2312
Tower 1031 BHK2312
Tower 2GF1 BHK2312
Tower 211 BHK2312
Tower 221 BHK2312
Tower 231 BHK2312
Tower 3GF1 BHK2312
Tower 311 BHK2312
Tower 321 BHK2312
Tower 331 BHK2312
Tower 4GF1 BHK2312
Tower 411 BHK2312
Tower 421 BHK2312
Tower 431 BHK2312
Tower 5GF1 BHK2312
Tower 511 BHK2312
Tower 521 BHK2312
Tower 531 BHK2312
Tower 6GF1 BHK2312
Tower 611 BHK2312
Tower 621 BHK2312
Tower 631 BHK2312
Tower 7GF1 BHK2312
Tower 711 BHK2312
Tower 721 BHK2312
Tower 731 BHK2312
Tower 8GF1 BHK2312
Tower 811 BHK2312
Tower 821 BHK2312
Tower 831 BHK2312
Tower 9GF1 BHK2312
Tower 911 BHK2312
Tower 921 BHK2312
Tower 931 BHK2312

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

GHAZIABAD DEVELOPMENT AUTHORITY

Competent authorityPromoter type
26Registered projects
24Projects
1City
2017–2026Active
Timelineevery project, start → promised completion
Construction of 560 EWS multistoried houses at RajCONSTRUCTION OF 348 MULTI STOREY E.W.S FLATS IN BLConstruction of 463 Multistoried Apartments on GH-Construction of 660 Multistoried Apartments on GH-896 EWS houses (Four Storied) Indraprastha AwasyiaConstruction of 80 MMIGflats in Nyaya Khand-3, IndConstruction of 120 multi storey houses ChandrashiCOnstruction of Four Storied 320 EWS houses at BegConstruction of 856 Multistorey Apartments (Samajw504 Multistorey Flats at GH-11,12 in Koyal Enclave266 Multistorey Flats at GH10 in Koyal Enclaveconstruction of 259 multi storied flat at GH-9Construction of two hundred fifty six flats at Madhuban Bapudham SchemeConstruction of EWS Houses under Pradhan Mantri awas Yojana at Madhuban Bapudham Scheme Pocket B.CONSTRUCTION OF 192 HOUSES AT POCKET-D INDRAPRASTH YOJANA LONI GHAZIABADConstruction of 432 EWS units under PMAY Scheme at Dasna GhaziabadConstruction of 288 EWS Houses Under PMAY at Masuri, Ghaziabad (Part-A)MADHUBAN BAPUDHAM SCHEME POCKET D COMMERCIAL COMPLEXConstruction of 1152 EWS Houses (PART-B) Under PMAY Scheme in Masoori GZB.Construction 720 EWS (G+3) Houses under PMAY Scheme at Pratap Vihar Scheme, Sec-11 GhaziabadConst. of 480 EWS (G+3) houses under PMAY scheme at Noornagar, Khasra no. 315, 343, 351, 352 in Raj nagar ExtensionConstruction of 528 EWS(G+3) at Rajaswa gram niwari, modinagar under PMAY scheme.C/o of 480 EWS (G+3) houses and development of 1200 buildings under PMAY scheme at Pratap vihar, GhaziabadRESIDENTIAL SCHEME (kH.NO-96,97) FOR NANDGRAM VILLAGE NOOR NAGAR GHAZIABAD
Builder DNAthe whole portfolio, summed
77,279 homes · 77 plotson the public record across 24 projects
17,873 sq mplotted area
3,53,543 sq mland declared
₹1179538.78 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Ghaziabad
Tehsil
Ghaziabad
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.5km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 394 m · Ghaziabad BypassPrimary road 2.5 km · Meerut RoadRailway line 2.6 kmMetro station 2.5km away (Hindon River)Limited bus connectivity nearby
Water & environment
Water body 180 mRiver 601 m · Hindon River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹38.86 Cr declared to build 480 flats. What that works out to:

₹8.10 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan
approved 14 Aug 2020 · 5 yrs ago
Building Permit no. 113/4/EEZONE-1/2020

The promised possession date (31 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 113/4/EEZONE-1/2020 on the approving authority’s portal to confirm the sanction.

Complaints register

None on record with UP-RERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.