11 of 16 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
560 sq m
Floor area
1,671 sq m
Description
THE JORD
Timeline
Project startedMay 2019
RERA registeredSep 2021
Proposed completionSep 2021
TodaySep 2026
Construction progress
88% overall, as filed
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the builder's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.
Find your flat
Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.
5 of 16 available
TypeArea sq mAvailable
3BHK820 of 1
3BHK750 of 2
2BHK631 of 3
2BHK612 of 3
2BHK591 of 2
2BHK590 of 2
1BHK441 of 2
1BHK420 of 1
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the builder declared — not a live booking system.
Complete project overview — done
02
Builder’s track record
K-RERA · Builder registration
VAIPPIL VILLAS AND APARTMENTS
PartnershipPromoter type
Ernakulam, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.
Planning authoritiesthis builder's portfolio, by approving body
Kochi Municipal CorporationMunicipal Corporation1 of 3 projects
ThrikkakaraLocal body (LSGI)this project1 of 3 projects
Thrikkakara MunicipalityMunicipality1 of 3 projects
Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Expressway 1.1 km · Salem - Kochi - Kanyakumari RoadPrimary road 26 mRailway line 3.2 kmMetro station 2.0km away (Palarivattom)3 bus stops within 500m
Water & environment
Canal 309 m · ChithrapuzhaWater body 432 m
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the builder at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Location — done
04
Government Guidance Rate
Kerala Registration Department — fair value
In Kerala it’s called the fair value.
₹15,065per sq yd
₹18,018per sq m
Which rate
Residential Plot with private road access
Matched to
The value published for this project's own survey number, in “Vazhakkala”.
What this number is — and isn’t
The minimum value Kerala’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
Not a market price. Sales normally register above it, and how far above varies by place and by project.
Its fit depends on the grain the state publishes at. This one is matched at the level of parcel, and says so above. How Horizon decides what to show.
Government Guidance Rate — done
05
Planning authority
K-RERA · Approved building plan
Thrikkakara
Local body (LSGI)
approved 12 Apr 2019 · 7 yrs ago
Building Permit no. TP1-BA(104737)/2019Survey no. S-17/7 R-191/12
The promised possession date (30 Sep 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
Verify it yourself — look up plan TP1-BA(104737)/2019 on the approving authority’s portal to confirm the approval.
The approving body, at scale
The local self-government (LSGI)
The local body that approved this project. It has approved 404 RERA projects across 14 districts — about 1 in 4 in Kerala.
Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
Planning authority — done
06
Complaints & litigation
K-RERA · public record
Complaints register
Not published. K-RERA doesn’t publish a complaints register in the record Horizon reads.
So there is nothing to count here — which is not the same as nothing having been filed.
What the builder declared
Declared to K-RERA
Litigation
None declared in this filing
Only what the builder declared, or what K-RERA records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with K-RERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
07
Other projects nearby
The register · within 25 km
189 residential projects still under way within 25 km. Step out ring by ring:
Of the 274 projects the radar draws within 6 km — every kind, every stage — 111 are residential projects still under way. This list keeps only those, and looks further out.
8 projects within 1 km — showing the nearest 6.
EDAPPALLY SOUTHResidential (Apartment)
ANVITA RENOVA
ANVITA BUILDERS PVT LTD
1 yr 10 mo
Sep 2024registered
Jul 2026target completion
Government Guidance Rate₹17,659/sq ydScale15 flatsAuthorityK-RERA
The approving body's other projects: counted by Horizon across the register.
06Complaints & litigation
K-RERA's public record lists no complaints or litigation for this project.
07Other projects nearby
The RERA-registered projects Horizon holds within 25 km of these coordinates.
Compiled by Horizon from public records. Each fact is reproduced as its source publishes it, and Horizon does not verify filings on the ground. The live record: gethorizon.in/projects/the-jord-vazhakkala-ernakulam-q3vr46uu.
Horizon does not rate, review, score or signal, and it gives no verdict, opinion or forecast. Its only aim is to seek the truth through data: what the public record says, where each fact comes from, and where the record is silent. Nothing in this document is legal, financial or investment advice; what to make of it is yours to decide.