HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
64 units
Mix
30 × 2BHK · 30 × 3BHK · 4 × PENT HOUSE
Booked
42 of 64 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
2,627 sq m
Floor area
10,133 sq m
Description
OLIVE IANTHA

Timeline

Project startedJul 2014
RERA registeredJul 2021
Proposed completionSep 2021
TodayJul 2026
Construction progress

88% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

22 of 64 available
TypeArea sq mAvailable
PENT HOUSE951 of 1
PENT HOUSE1581 of 1
2BHK885 of 15
3BHK1049 of 30
2BHK736 of 15
PENT HOUSE1290 of 1
PENT HOUSE760 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

OLIVE BUILDERS

PartnershipPromoter type
Ernakulam, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
3Projects
1City
2021–2026Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
119 homeson the public record across 3 projects
22,706 sq mbuilt-up filed
5,705 sq mland declared
₹9.09 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Municipal Council Of KalamasseryLocal body (LSGI)this project1 of 2 projects
Thiruvalla Municipality PathanamthittaLocal body (LSGI)1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
V P Marakkar Road
Village
THRIKKAKARA NORTH
Taluk
Kanayannur
District
Ernakulam
Pincode
682024
Survey no.
5/122/1-2
Patta no.
30239
What’s nearby
SchoolsNearest school 1.3km away · College or university 1.8km away · Library 1.3km away
HealthcareHospital 441m away · Clinic within 2km · Pharmacy within 1km
LifestylePark 1.3km away · Gym or sports centre 826m away · 11+ restaurants and cafes within 1km
ShoppingSupermarket 805m away · Mall 193m away · Bank 860m away
Getting around
Expressway 741 m · Kodungallur-Paravur-Ernakulam HighwayPrimary road 1.2 kmRailway line 554 mMetro station 1.1km away (Pathadipalam)Bus stop within 1km
Water & environment
Water body 414 mCanal 527 m · Chithrapuzha
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Municipal Council Of Kalamassery

Local body (LSGI)
approved 19 Jul 2014 · 12 yrs ago
Building Permit no. BA-393/14Survey no. 5/122/1-2

The promised possession date (30 Sep 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan BA-393/14 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

The local self-government (LSGI)

The local body that sanctioned this project. It has approved 404 RERA projects across 14 districts about 1 in 4 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.